Critical Minerals Group (ASX:CMG) has advised shareholders to place no reliance on the Pre-Feasibility Study (PFS) for its Lindfield Vanadium Project, disclosing that material assumptions underpinning the study's financial information are not able to be supported and have materially changed, requiring a correction and revision to be published.

Key Points

  • The company has identified that material assumptions underpinning certain financial assumptions of the Lindfield PFS, originally released on 20 and 21 July 2026, cannot be supported.
  • The principal assumption affected is the capital cost estimate, specifically project delivery costs and the basis on which the 3 Mtpa case was derived from the 4 Mtpa estimate.
  • The company also intends to revise reagent prices and consumption rates within the operating cost estimate, and the treatment of taxation, including tax depreciation method and the Critical Minerals Production Tax Incentive.
  • The mine plan, vanadium pentoxide and vanadium electrolyte price assumptions, processing flowsheet and metallurgical recoveries are not affected by the review.
  • The Mineral Resource Estimate reported on 10 May 2024 is not affected, and the Definitive Feasibility Study drilling program at Lindfield is continuing.

PFS Correction and Revision to Capital Cost Assumptions

Critical Minerals Group disclosed on 26 November 2026 that its review of the Lindfield Vanadium Project PFS — released on 20 and 21 July 2026 — has identified that material assumptions underpinning the study's financial information cannot be supported. The principal assumption concerned is the capital cost estimate, in particular the project delivery costs included in it and the basis on which the 3 Mtpa case was derived from the 4 Mtpa estimate. The company said the impact of the changes to these material underlying assumptions is expected to negatively impact certain forecast financial information previously published in the PFS.

Operating Cost and Taxation Assumptions Under Review

Beyond the capital cost estimate, the company said it also intends to revise reagent prices and consumption rates within the operating cost estimate. The treatment of taxation is also subject to revision, including the tax depreciation method and the Critical Minerals Production Tax Incentive. The company stated that the mine plan, the vanadium pentoxide and vanadium electrolyte price assumptions, the processing flowsheet and the metallurgical recoveries are not affected by these revisions. The company said it intends to publish an updated and revised PFS as soon as practicable.

Mineral Resource Estimate and Definitive Feasibility Study Unaffected

The company confirmed that the Mineral Resource Estimate reported on 10 May 2024 is not affected by the review. The Definitive Feasibility Study drilling program at Lindfield is continuing. The company stated it is not aware of any new information or data that materially affects the information included in the original Mineral Resource Estimate announcement, and that all material assumptions and technical parameters underpinning the estimate continue to apply and have not materially changed. Until the corrected PFS is published, shareholders have been advised to place no reliance on the prior PFS or the forecast financial information contained within it.