Critical Minerals Group Limited (ASX:CMG) has completed the first rotation of its Definitive Feasibility Study drilling program at the Lindfield Vanadium Project in north-western Queensland, with 16 holes drilled and all twinned holes for metallurgical test work finished, the company disclosed on 18 November 2026.

Key Points

  • First rotation of the DFS drilling program at Lindfield Vanadium Project completed with 16 holes drilled.
  • All twinned holes planned for bench-scale variability test work and metallurgical pilot plant program have been drilled, with core transported from site.
  • Two groundwater monitoring bores drilled to target depths and developed; monitoring probes to be installed in the second rotation.
  • Second and final rotation now underway, focused on perimeters of the PFS mine development area and a contiguous zone to the south of the current Mineral Resource.
  • Consolidated program expected to achieve all four goals but at a lower drill hole density than the approximately 55 holes initially planned.

First Rotation Drilling Details at Lindfield

Drilling contractor J&S Drilling mobilised to site on 26 October 2026, with drilling commencing the following day on pre-developed drill tracks and pads. Geological supervision was provided by Measured Group. The 16 holes completed during the first rotation included all twinned holes required to supply core for bench-scale variability test work and feed for the metallurgical pilot plant program, which the Pre-Feasibility Study identified as the highest value lever for the project. That core has been transported from site. The Lindfield Vanadium Project is located approximately 30 kilometres east of Julia Creek in north-western Queensland.

Groundwater and Geotechnical Work Completed

Two of the planned groundwater monitoring bores were drilled to target depths and developed during the first rotation, adding to the three existing monitoring bores at the project. Monitoring probes will be installed during the second rotation, with the bores intended to provide baseline groundwater level and quality data for the environmental approvals program. Geotechnical work was also completed, comprising standard penetration tests and collection of samples for unconfined compressive strength testing, described in the filing as providing site-specific data for engineering design work in the DFS. CMG's Chief Technology Officer Nicola Semler and Competent Person Adrian Buck of Measured Group visited site on 3 November 2026.

Second Rotation Scope and Mineral Resource Considerations

The second and final rotation commenced during the week of the filing and is focused on resource drilling to increase geological confidence on the northern, southern and eastern perimeters of the PFS mine development area, as well as expanding resource definition within the geologically contiguous zone directly to the south of the current Mineral Resource. The full area planned will be drilled, but at a lower drill hole density than the approximately 55 holes initially planned. The filing states that some mineralised material in the southern area may be classified as Inferred rather than Indicated, as determined by the Competent Person in the updated Mineral Resource Estimate. Results will be reported once received and reviewed. The filing states there is no certainty that drilling will result in any change to the Mineral Resource.