Clara Resources Australia Limited (ASX:C7A) has identified five new exploration targets on EPM 28652 at its Mareeba Gold Project in Far North Queensland, following a systematic review of an expanded high-resolution LiDAR survey flown in August 2026, with two targets — Kentucky and Harrington — prioritised as immediate drilling opportunities.
Key Points
- Five new targets identified on EPM 28652 from LiDAR terrain model and historic records, with no field mapping, sampling or ground disturbance conducted
- Kentucky and Harrington prioritised as immediate drilling opportunities, with access from sealed roads on a single pastoral lease
- The expanded LiDAR survey was flown between 9 and 13 August 2026 at 20 points per square metre, more than twice the density of the original March survey
- No drill holes recorded within 2 km of the Kentucky target, according to the company's database
- Clara is assessing how Kentucky and Harrington can be incorporated within its existing planned drilling program at Mareeba
LiDAR Survey Methodology on EPM 28652
The expanded LiDAR survey was flown between 9 and 13 August 2026 at 20 points per square metre, more than twice the density of the original March survey. Over EPM 28652, the company gridded the classified ground points to a 0.25-metre bare earth terrain model. Clara applied the same approach used to generate its first seven targets along the Kingsborough Fault corridor in May 2026, examining each historic occurrence recorded by the Geological Survey of Queensland in the terrain model, then reviewing the whole permit for surface features of the same form, checking each against open file reports and the historic mining lease register.
Details of the Five EPM 28652 Targets
The five targets identified are Kentucky, Harrington, Lost Reef, Granola, and Kimalo North. Kentucky is listed as a historic gold mine, with an ore pile sample assaying 4.4 g/t Au and a stope 6 metres wide and 8 metres long recorded in underground workings. Harrington presents dump samples to 2.14 g/t Au and quartz vein diggings along strike for 200 metres, with ten workings including a NNW line of approximately nine shafts over 85 metres. Granola records rock chips to 8 g/t Au and 8% Sb from three quartz veins within 10 metres. Kimalo North records a dump sample of 13.4 g/t Au. No historical production records are available for Kentucky or Harrington specifically.
Kentucky and Harrington as Priority Drilling Targets
Clara's geologists have prioritised Kentucky and Harrington as immediate drilling opportunities based on the scale of their historic workings and their access from sealed roads, with tracks already running to the old workings at each. At Kentucky, the terrain model resolves an east-west costean line, two converging costeans beside the recorded mine position, and a pit group with a rectangular costean grid approximately 150 metres to the east-south-east, where the main pit is 3.5 metres deep. The company's database records indicate no drill holes within 2 km of Kentucky. Clara Executive Director Duncan Gordon stated the company is now assessing how Kentucky and Harrington can fit within the drilling program already planned at Mareeba.