Carnegie Clean Energy (ASX:CCE) has released a November 2026 webinar presentation disclosing the status of its ACHIEVE Programme CETO wave energy deployment in the Basque Country, Spain, with full system deployment at BiMEP targeted for European Spring 2027 and work commenced on a 6 MW CETO array project at the same site.

Key Points

  • The ACHIEVE Programme's Build & Deploy phase (Phase 3) is 80% complete, with Carnegie ranked first of 36 applicants at the start of that phase.
  • Total funding for the EuropeWave contracted deployment stands at €7.05 million, comprising a €3.75 million EU EuropeWave Phase 3 award, €1.2 million from the Spanish Government (IDAE – Renmarinas, December 2023), and €2.1 million from Basque agency EVE (March 2024).
  • Full system deployment, including moorings, dynamic cable, and grid connection, is scheduled for European Spring 2027.
  • Work has commenced on a 6 MW project comprising six 1 MW CETO units at BiMEP, off the coast of the Basque Country, Spain, with other sites under consideration in the EU, UK, US, and Australia.

ACHIEVE Programme Phase 3 Build and Deployment Progress

According to the filing, Carnegie's ACHIEVE Programme is designed to demonstrate commercial, technical, and operational objectives for commercial-scale CETO wave energy technology across six defined objectives including energy capture, control systems, survivability, and operations. Phase 1 (Concept and tank test) and Phase 2 (Preliminary design) are confirmed complete. Phase 3, the Build and Deploy phase, is disclosed as 80% complete. The Buoyant Actuator has been assembled and deployed at BiMEP as a Stage 1 deployment milestone, with generator modules currently being assembled at SKF. Power take-off testing has been conducted onshore in Bilbao using model data sets to simulate real ocean motion conditions.

Full System Deployment Sequence Scheduled for European Spring 2027

The filing outlines a three-step full system deployment sequence planned for European Spring 2027. The sequence begins with the deployment of primary and secondary mooring systems, followed by the dynamic cable connection to the export cable, and concludes with full system deployment including grid connection. The company stated the post-winter timing is intended to minimise commercial weather risk. Following deployment, operation is designed to validate controllers, deep diving capability, power performance, and reliability of components. CETO units carry a WEC rating of 1,000 kW, a spatial density of 30 MW per square kilometre, and a capacity factor range of 30 to 50%.

Near-Term Projects, Funding Strategy, and Revenue Model

Carnegie disclosed that the ACHIEVE Programme deployment and grid connection is expected within six months, and that work has commenced on a 6 MW project at BiMEP. The company's near-term funding strategy involves project consortiums predominantly funded by government bodies and energy utilities, with funding programs described as underway or planned in the EU, UK, and US. Carnegie's stated revenue generation model includes the sale of integrated CETO units, sale of wave prediction and control system software, and engineering services including project management, CETO array maintenance and operations spanning 20 or more years, and software development.