Carbine Resources (ASX:CRB) has completed its Phase 1 vacuum drilling program at the Down South Silica Sand Project located approximately 10km southeast of Bunbury in Western Australia, with 74 drill holes finished and a Phase 2 program receiving Programme of Work approval, targeted for completion before Christmas 2026.
Key Points
- Phase 1 vacuum drilling program completed at Down South Silica Sand Project (E70/5823), with 74 drill holes finished and a maximum depth of 6.3 metres.
- Of the 74 holes completed, 53 were less than 1 metre deep, 12 reached between 1 and 2 metres, and 9 exceeded 2 metres.
- The original program targeted approximately 120 drill holes to depths of up to approximately 10 metres; difficult ground conditions restricted progress.
- Programme of Work approval received for Phase 2, targeting the Central Zone of E70/5823, with drilling to be completed before Christmas 2026 subject to rig availability and ground conditions.
Phase 1 Drilling Results at E70/5823
The Phase 1 vacuum drilling program was undertaken on exploration licence E70/5823 to investigate priority silica sand target areas. A total of 74 holes were completed, with the deepest reaching 6.3 metres. The program had originally targeted approximately 120 drill holes to depths of up to approximately 10 metres. Difficult ground conditions, including a shallow groundwater table, restricted the vacuum drilling equipment from advancing to planned depths, and a number of the planned holes were not drilled as a result. Selected samples collected during the program will be submitted for laboratory analysis, with assay results to be reported in due course.
Down South Silica Sand Project Overview
The Down South Silica Sand Project is located approximately 10km southeast of Bunbury in Western Australia's South West region. The project comprises three granted exploration licences — E70/5823, E70/6414, and E70/6415 — covering approximately 5,800 hectares. According to the filing, the area has been subject to numerous historical drilling programs, including work undertaken by Westralian Sands prior to 1970, which identified several areas of interest and ultimately led to a small mining operation to test the economics of a potential silica sand export project.
Phase 2 Drilling Program Planned for Central Zone
Carbine Resources disclosed that Phase 2 drilling is planned to test additional silica sand targets in the Central Zone of E70/5823. Programme of Work approval has been received for the Phase 2 program, with drilling targeted to commence before Christmas 2026, subject to rig availability and suitable ground conditions. The Phase 2 program is also planned to incorporate selected higher priority drill locations from Phase 1 where planned depths could not be achieved. The company stated it is reviewing Phase 1 outcomes and ground conditions encountered to finalise planning for the next phase, including rig selection and confirmation of the highest priority targets.