Capstone Copper Corp. (ASX:CSC) has revised the lower end of its 2026 consolidated copper production guidance to 195 thousand tonnes, down from 200 thousand tonnes, following an extended outage of the primary crusher at its Pinto Valley operation in Arizona, with recommissioning now expected in mid-December 2026.

Key Points

  • Pinto Valley primary crusher recommissioning pushed to mid-December 2026, with partial concentrator restart using temporary mobile crushing equipment expected in mid-November at up to 40 thousand tonnes per day interim throughput.
  • The extended downtime is expected to impact 2026 copper production by approximately 5,000 tonnes over the remainder of the year.
  • 2026 consolidated copper production guidance lower end adjusted to 195 thousand tonnes from 200 thousand tonnes originally.
  • A national strike in Chile initiated by a civic movement and independent trucking associations presents a risk to concentrate and cathode shipments and delivery of key consumables including fuel and sulphuric acid, though production at Mantoverde and Mantos Blancos remains unimpacted at this time.

Pinto Valley Crusher Outage and Interim Operating Arrangements

According to the filing dated November 12, 2026, the primary crusher at Capstone's Pinto Valley operation is now expected to be recommissioned in mid-December 2026. A partial restart of the concentrator using temporary mobile crushing equipment is expected in mid-November 2026, with an estimated interim throughput capacity of up to 40 thousand tonnes per day. The Company disclosed that the additional downtime is expected to impact 2026 copper production by approximately 5,000 tonnes over the remainder of the year, prompting the adjustment to the lower bound of its production guidance.

2026 Consolidated Copper Production Guidance Revision

Capstone disclosed it is adjusting the bottom end of its 2026 consolidated copper production guidance to 195 thousand tonnes, from 200 thousand tonnes originally. The filing noted that 2026 consolidated copper production guidance includes a full year of results from Cozamin, which is pending sale to Luca Mining Corp., with further details available in a press release dated September 21, 2026. No change to the upper end of guidance was disclosed in the filing.

Chilean National Strike and Operational Risk at Mantoverde and Mantos Blancos

The filing disclosed that a national strike has been initiated in Chile by a civic movement and a coalition of independent trucking associations in response to elevated fuel prices. Capstone stated the strike presents a risk to 2026 production expectations associated with the suspension of ongoing national concentrate and cathode shipments and the delivery of key consumables such as fuel and sulphuric acid. The Company noted that production at both its Mantoverde and Mantos Blancos operations remains unimpacted by the strike at this time.