Capricorn Metals (ASX:CMM) disclosed at its 2026 Annual General Meeting that the company generated operating cashflow of $470 million and a net profit after tax of $327 million in FY26, while Group Ore Reserves grew 33% to 5.24 million ounces across its two Western Australian gold projects.
Key Points
- FY26 operating cashflow of $470 million and net profit after tax of $327 million disclosed at the 2026 AGM
- Karlawinda Gold Mine produced a record 124,000 ounces of gold in FY26 at an AISC of A$1,629/oz
- Mt Gibson Ore Reserve stands at 3.7 million ounces, including a maiden underground reserve of 365,000 ounces, with a 19-year mine life and forecast steady-state production of 260,000 ounces per annum
- Cash and bullion on hand grew to $535 million by end of September, up from $508 million at financial year-end
- Two fully franked dividends of 5 cents per share each were paid in April and October
Karlawinda Gold Mine FY26 Production and Expansion
The Karlawinda Gold Mine in the Pilbara delivered record production of 124,000 ounces of gold in FY26 at an all-in sustaining cost of A$1,629 per ounce, according to the filing. The company stated the operation has returned $1 billion in cash from 600,000 ounces of gold production over five years. A major capital project to expand processing facilities from 4 to 6.5 million tonnes per annum was commissioned in September, described as on time and on budget. Karlawinda's Ore Reserves stand at 1.57 million ounces following a biennial update, supporting a ten-year mine life at 150,000 ounces per annum.
Mt Gibson Development Project Status and Updated PFS
The Mt Gibson project in the Murchison holds 3.7 million ounces of gold reserves, including a maiden underground reserve of 365,000 ounces at the Orion South deposit. An updated Prefeasibility Study released in the year incorporated underground mining for the first time, projecting steady-state production of 260,000 ounces per annum over a 19-year mine life at an AISC of A$1,870 per ounce. At a gold price of A$5,500, the project's pre-tax NPV is stated at $6.1 billion from $12 billion of free cash flow. The company received its Federal environmental permit in June and is progressing through the final stages of the State EPA approval process.
Range 500 Strategy and Golden Range Processing Hub Concept
Capricorn Metals outlined its Range 500 aspiration, targeting 500,000 ounces per annum production within five years, underpinned by high-grade underground material at Mt Gibson and assets acquired through the Warriedar Resources acquisition. The company holds more than 4,500 square kilometres across the belt, including a 1.4 million ounce resource at Golden Range, located approximately 80 kilometres north of Mt Gibson and linked by an established haul road. An early concept involves constructing a 1.5 to 2.5 million tonne per annum processing hub at Golden Range to treat open pit ore and surplus high-grade underground ore trucked from Mt Gibson. A maiden Lexington underground resource is expected in the current quarter.