Boab Metals Limited (ASX:BML) has released its 2026 Annual General Meeting shareholder update, disclosing construction progress at its 100%-owned Sorby Hills silver-lead project in Western Australia's East Kimberley region, with first concentrate production targeted for Q4 2027.

Key Points

  • Sorby Hills accommodation camp is 80% complete and in use, with the access road complete and bulk earthworks commenced.
  • DeGrussa plant deconstruction is complete, with more than 120 equipment trailers received at Sorby Hills and plant relocation commenced.
  • The Mineral Resource stands at 50.6 Mt at 3.0% Pb and 34 g/t Ag, with an Ore Reserve of 18.3 Mt at 3.2% Pb and 37.3 g/t Ag, supporting a planned mine life of 10.5 years.
  • Cash and cash equivalents were A$30 million as at 30 September 2026, with a fully paid ordinary share count of 583.1 million as at 2 November 2026.
  • Financial close and first drawdown under a A$236 million syndicated facility remain subject to conditions precedent, with both targeted in Q4 2026.

Sorby Hills Construction Status as at November 2026

According to the filing, construction at Sorby Hills is advancing across multiple workstreams. The accommodation camp is 80% complete and in use, the access road is complete, and bulk earthworks have commenced. The DeGrussa processing plant, acquired by Boab Metals in May 2026 alongside an EPC contract awarded to GR Engineering Services for its relocation, has been fully deconstructed. More than 120 equipment trailers have been received at the Sorby Hills site. DeGrussa plant foundations have commenced and relocation is under way. The filing also states that more than 90% of the tailings storage facility keyway has been excavated.

Key Milestones and Agreements Disclosed in the Filing

The filing outlines a series of milestones reached through 2025 and 2026. The Board approved the Final Investment Decision on 17 December 2025, with Boab completing 100% acquisition of Sorby Hills on 27 January 2026. Western Australia approved the Mining Proposal and Mine Closure Plan in March 2026. The A$236 million syndicated facility reached contractual close on 24 April 2026. A six-year diesel supply agreement was signed, and a mining services heads of agreement with RE:GROUP was executed on 28 September 2026. The company's equity programme totalled A$117 million, comprising a A$60 million placement, a A$7 million share purchase plan, and a A$50 million October 2025 placement.

Upcoming Newsflow and Remaining Ore Reserve Details

The filing identifies several items of expected newsflow. Financial close and first drawdown under the A$236 million syndicated facility are targeted in Q4 2026, subject to conditions precedent. A final mining services contract with RE:GROUP is also targeted in Q4 2026. The company disclosed it is looking to award the remaining 50% of offtake for the early years of mining in the Q4 2026 to Q1 2027 period. Final drill results from the 48-hole, 6,765-metre Phase IX program, including Omega Central and the Keep zinc target, are also expected in Q4 2026. First concentrate production at Sorby Hills is targeted for Q4 2027.