Key Highlights
- The definitive feasibility study, released in August, outlines an open-pit operation processing 5.25 million tonnes a year over a mine life of more than 14 years.
- Using a base gold price of US$3,600 an ounce, the study gives a post-tax net present value of US$1.2 billion and an internal rate of return of 41%, with payback in about 21 months.
- WIA reported cash of A$229.2 million and no Debt at 30 September 2026, following a A$125 million Placement in August.
- On the company's indicative timetable, construction would run from about the first half of 2027 into the second half of 2028, with first gold around 2029.
WIA Gold Ltd (ASX:WIA) is advancing the Kokoseb gold project in Namibia. Permitting and financing remain important steps towards the project's proposed development. The company’s shares were trading at AUD 0.37 at 3:42 PM AEDT on 26 November 2026, up 8.82% for the session.
Kokoseb: from study to development
WIA's focus is the Kokoseb gold project in Namibia's Erongo region. According to the corporate presentation it lodged on 19 November 2026, Kokoseb holds a mineral resource of 3.78 million ounces of gold, including a maiden underground inferred resource of 0.56 million ounces at 2.2 grams per tonne, and a maiden probable ore reserve of 1.95 million ounces.
The definitive feasibility study, released in August, outlines an open-pit operation processing 5.25 million tonnes a year over a mine life of more than 14 years. It forecasts average output of about 150,000 ounces a year over the first decade, at an All-In Sustaining Cost of US$1,696 an ounce.
Pre-production Capital is estimated at US$475 million. Using a base gold price of US$3,600 an ounce, the study gives a post-tax net present value of US$1.2 billion and an internal rate of return of 41%, with payback in about 21 months. At the July 2026 average Spot Price of US$4,075 an ounce, the presentation puts the NPV at US$1.6 billion. The company has also outlined spending of about US$9.3 million to keep open the option of expanding the plant to around 7 million tonnes a year, though it describes that expansion as conceptual.
Funding and the next milestones
WIA reported cash of A$229.2 million and no debt at 30 September 2026, following a A$125 million placement in August. It has indicative, non-binding terms for a US$360 million senior secured debt Facility from Sprott, together with a US$15 million Equity subscription.
The presentation targets financial close in the fourth quarter of 2026, subject to due diligence, final documentation and the grant of a Mining licence and environmental clearance certificate, both also expected this quarter. Those two permits are the next confirmed milestones. On the company's indicative timetable, construction would run from about the first half of 2027 into the second half of 2028, with first gold around 2029.
Gold price backdrop
Gold has been weaker in recent weeks. Reuters, as reported by the New Straits Times on 18 November, said spot gold had fallen to its lowest level in more than a year, near US$3,760 an ounce, amid expectations of further US Interest Rate rises. That remains above the DFS base-case assumption, but a lower gold price would narrow project margins.
Risks
WIA is a developer, not a producer, and will not generate Revenue from Kokoseb for several years. The debt terms are non-binding, and both financial close and construction depend on Namibian permits being granted on schedule.
Large-scale gold projects also face construction cost and timing risk, and a further fall in the gold price would weigh on the study's returns. Shareholders could face dilution if additional equity is required.
Until WIA announces progress on its permits or financing, there is no confirmed company-specific reason for today's move.