Key Highlights

  • According to its Quarterly Report of 27 October 2026, the project's resource stands at 43.6 million tonnes at 1.1 g/t gold for about 1.51 million ounces.
  • The quarterly report also noted metallurgical testwork for the pre-feasibility study showing gold extraction of up to 99.4%.
  • On 8 October 2026, PC Gold agreed to buy the last third-party Mining leases inside the project area, along with a water licence and production bore.
  • The company has also applied for a new mining Lease covering about 443 hectares, which would enlarge the Spring Hill lease area by about 43% if granted.

PC Gold Ltd (ASX:PC2) is developing the Spring Hill gold project in the Northern Territory. Resource definition, metallurgical assessment and consolidation of project tenure are central to its current work programme. The company’s shares were trading at AUD 0.76 at 3:34 PM AEDT on 26 November 2026, up 7.86% for the session.

The Spring Hill project

PC Gold's main asset is the Spring Hill gold project near Pine Creek in the Northern Territory, which it owns outright. According to its quarterly report of 27 October 2026, the project's resource stands at 43.6 million tonnes at 1.1 g/t gold for about 1.51 million ounces. That is 84% higher than in June 2024.

About two-thirds of those ounces are in the indicated category. The resource also includes a maiden estimate for the higher-grade Link Zone, of 1.12 million tonnes at 5.37 g/t for about 194,000 ounces.

October drilling results reported thick, stacked intercepts at Spring Hill and a new high-grade zone in the style of the Link Zone. The quarterly report also noted metallurgical testwork for the pre-feasibility study showing gold extraction of up to 99.4%.

Consolidating the footprint

On 8 October 2026, PC Gold agreed to buy the last third-party mining leases inside the project area, along with a water licence and production bore. According to its quarterly report, the price is A$6.5 million, made up of A$4.5 million in cash and A$2.0 million in shares. Completion is expected on or after 8 December 2026, subject to ministerial approval.

The company has also applied for a new mining lease covering about 443 hectares, which would enlarge the Spring Hill lease area by about 43% if granted.

On 29 October it released a regional targeting review covering about 10,300 hectares. The review identified 37 targets outside the current resource, 16 of them ready for drilling.

Funding and share register

The company is well funded for an explorer. It held A$85.5 million in cash at 30 September 2026, after a A$75 million Placement at A$1.05 a share. Its shares now trade below that placement price.

The register is also changing. Perennial Value Management became a substantial holder on 29 October 2026, with 5.06%. A notice lodged on 19 November showed that RIVI PC Gold's voting power had fallen to 15.26%, after an on-market sale and dilution from placements.

Risks

PC Gold is not yet producing, and its average grade of around 1 g/t means project Economics will depend on scale, costs and the gold price. About a third of the resource ounces are inferred, which carries lower geological confidence. The footprint Acquisition still needs ministerial approval, and the new lease application is pending. A move to production would need studies, permits and funding that are not yet in place.

Next milestones

PC Gold is targeting an updated resource estimate for December 2026. It also expects to complete its pre-feasibility study in the fourth quarter of calendar 2026. Drilling of the first priority regional target, Steve's Gully, was due to begin within about three weeks of the 29 October update.