Key Highlights

  • Boab owns 100 per cent of the Sorby Hills silver-lead project in the East Kimberley region of Western Australia.
  • The project delivery plan released on 29 September 2026 put total Capital costs at A$262 million, with about A$205 million remaining at that point, including contingency.
  • The updated ore reserve stands at 18.3 million tonnes at 3.2 per cent lead and 37.3 grams per tonne silver, according to the AGM presentation.
  • The September quarter report, released on 27 October 2026, showed cash of A$29.9 million, down from A$60.9 million as construction spending ramped up.

Boab Metals Ltd (ASX:BML) is developing the Sorby Hills silver-lead project in Western Australia. Construction progress and the conditions attached to project financing are central to its development timetable. The company’s shares were trading at AUD 0.30 at 3:40 PM AEDT on 26 November 2026, up 18.00% for the session.

Context for the move

The rise comes after a lengthy decline.

Silver prices have also been volatile. Whether silver moved on 26 November, or whether that influenced Boab's shares, has not been verified. In its AGM presentation, the company argued that the recent sell-off reflected financial investors rather than weaker physical demand.

What Boab is building

Boab owns 100 per cent of the Sorby Hills silver-lead project in the East Kimberley region of Western Australia. The board approved a final Investment decision in December 2025.

The project delivery plan released on 29 September 2026 put total capital costs at A$262 million, with about A$205 million remaining at that point, including contingency. The plan targets average annual output of 2.1 million ounces of silver and 60,000 tonnes of lead over a mine life of about 10.5 years. Boab is relocating the former DeGrussa processing plant, bought from Sandfire Resources, to the site.

The updated ore reserve stands at 18.3 million tonnes at 3.2 per cent lead and 37.3 grams per tonne silver, according to the AGM presentation.

Funding and construction progress

The September quarter report, released on 27 October 2026, showed cash of A$29.9 million, down from A$60.9 million as construction spending ramped up. Boab has a A$236 million syndicated Debt Facility with Merricks Capital and Adare Finance, which remained undrawn at 30 September. First drawdown is expected in the December quarter, subject to conditions precedent. The facility carries 12 per cent fixed interest plus a 2.5 per cent annual fee.

The same report said bulk earthworks were on schedule, concrete works had begun in key plant areas, and the accommodation camp was nearing 132 rooms. A binding heads of agreement with RE:GROUP covers Mining services, with mining expected to start by March 2027. Trafigura holds offtake rights to half of the concentrate.

Timing and risks

The September delivery plan and October quarterly targeted first concentrate in the third quarter of 2027, but the AGM presentation of 23 November describes commissioning and first concentrate as targeted for the fourth quarter of 2027, adding that timing is indicative.

Key risks include meeting the conditions for financial close, construction cost and schedule pressure, the relatively high cost of debt and exposure to silver and lead prices. At the AGM, all five resolutions passed, though about 21 per cent of votes opposed the 10 per cent Placement capacity resolution.

Next milestones

According to the AGM presentation, Boab expects financial close and first drawdown in the fourth quarter of 2026, final Phase IX drilling results in the same period, and a definitive mining services agreement and award of the remaining offtake in late 2026 or early 2027.