Key Highlights

  • VHM (ASX:VHM) reported progress on project funding, approvals and construction preparation in its September 2026 quarterly report.
  • A binding rare earth concentrate offtake agreement covers production for the life of the current Mining licence.
  • A non-binding mineral sands offtake term sheet was announced after quarter-end.
  • The refreshed feasibility study estimates total project funding requirements of AUD 482 million.

VHM (ASX:VHM) is developing rare earths and mineral sands resources in north-west Victoria through its Goschen project. Its shares were trading at AUD 0.195 during the 25 November 2026 session, down 7.14%. The company’s September Quarterly Report outlines the commercial, engineering and regulatory milestones achieved as Goschen advances towards a potential construction decision.

Goschen offtake arrangements take shape

The September quarter report details a binding arrangement with Iluka Resources for the purchase of all rare earth concentrate produced over the life of the existing mining licence. The agreement provides a prospective domestic processing pathway through the Eneabba rare earth refinery. It also incorporates a convertible note funding package of up to AUD 40 million, structured across two tranches. The funding package is a component of the broader financing strategy rather than confirmation that all Capital required for construction has been secured.

After quarter-end, the developer reported a separate, non-binding term sheet with Mitsui for heavy mineral concentrate. The proposed arrangement covers up to 65,000 tonnes annually, representing half of planned concentrate production. An initial three-year term and a possible three-year extension are contemplated. Pricing would be linked to zircon and titanium dioxide market prices. Negotiations towards a binding agreement remain necessary.

Feasibility refresh establishes updated project economics

The September feasibility study refresh estimates a pre-tax, pre-corporate net present value of AUD 807 million at an 8% discount rate. The model indicates a 33% internal rate of return and a three-year payback period after commercial production begins. These figures are modelled outcomes rather than realised financial performance and depend on assumptions about costs, Commodity prices and operating conditions.

The study forecasts annual average Revenue of AUD 326 million and EBITDA of AUD 146 million before corporate costs over the mine life. Estimated execution capital stands at AUD 283 million, while the overall funding requirement is AUD 482 million. The distinction matters because execution capital does not encompass the entire financing requirement. Discussions with potential senior Debt financiers remain part of the development process.

Permitting and engineering preparations

The company secured approval of the Planning Scheme Amendment during September, addressing infrastructure outside the mining licence area, including road upgrades and the raw water pipeline. This completed the final major approval identified by management. Major tenders for the processing plant, water pipeline and road infrastructure have also been completed, positioning preferred contractor appointments to follow an Investment decision.

The company reported completion of 333 aircore holes totalling 11,164 metres across two project areas. Twin-hole results showed mean total heavy mineral grades 5.6% and 3.6% above corresponding historical drilling in Areas 1 and 3 respectively. The program supports further geological and processing evaluation, rather than establishing an automatic increase in the reported resource.

Funding remains the next development milestone

Cash at 30 September stood at AUD 10.2 million. The project has approved processing capacity of five million tonnes annually and a reported ore reserve of 220 million tonnes. The refreshed 18-year mine plan draws on less than half of that reserve. Management’s priorities include completing financing arrangements, converting the proposed mineral sands offtake into a binding contract and preparing for construction.

In the broader market, the S&P/ASX 200 stood at 8,657.60 during the 25 November session, down 0.79%.

Key Insights

The commercial arrangements and approval milestones address different components of project readiness. The next stage remains contingent on financing and a final investment decision. Project-level forecasts should not be interpreted as current revenue or earnings.

Q. What does Goschen plan to produce?
A. The project is designed to produce rare earth concentrate and heavy mineral concentrate.

Q. Is the mineral sands offtake binding?
A. No. The announced term sheet is non-binding and negotiations are continuing.

Q. How much funding does the refreshed study estimate?
A. The study identifies a total funding requirement of AUD 482 million.

Q. Has construction been authorised?
A. The company is progressing towards a final investment decision; major approvals alone do not establish that construction has commenced.