Key highlights
- Minerals 260 announced on 12 November 2026 that the Bullabulling Gold Project Works Approval has been granted.
- The approval covers the processing plant, power infrastructure and tailings storage facility, subject to further permits.
- The project hosts a Mineral Resource of 190Mt at 1.0 g/t gold for 6.2Moz.
- A final Investment decision is targeted for the first quarter of 2027, with first production targeted in 2028.
Minerals 260 (ASX:MI6) announced on 12 November 2026 that the Western Australian Department of Water and Environmental Regulation has granted a Works Approval for its 100%-owned Bullabulling Gold Project. The approval enables construction of key facilities including the processing plant, power infrastructure and tailings storage facility.
Approval Conditions and Remaining Permits
The Works Approval is subject to receipt of the Native Vegetation Clearance Permit and the Mine Development and Closure Proposal. The company said the remaining approvals for the project are under assessment through the Western Australian State approvals pathway and are on track to support the Board's final investment decision in the first quarter of calendar 2027.
Management Commentary
Managing Director Luke McFadyen described the grant as a milestone in the company's efforts to reduce development risk ahead of a first production target in 2028. He said receipt of the approval ahead of the investment decision reduces schedule risk and that the company looks forward to receiving the remaining approvals.
Project and Resource Details
Bullabulling is a potential open pit operation located 25km south-west of Coolgardie in the Eastern Goldfields region of Western Australia. The project hosts a JORC 2012 Mineral Resource Estimate of 190Mt at 1.0 g/t gold for 6.2Moz, on granted Mining leases, with an effective date of 8 July 2026. Indicated resources total 140Mt at 0.98 g/t for 4,400koz, and Inferred resources total 51Mt at 1.0 g/t for 1,700koz.
By deposit, Phoenix holds 74Mt at 0.95 g/t for 2,300koz and Bacchus holds 72Mt at 1.0 g/t for 2,400koz, while Dicksons, Kraken and Gibraltar hold 660koz, 540koz and 290koz respectively. The resource is reported above a cut-off grade of 0.35 g/t inside a A$5,250 per ounce pit shell and includes the project's maiden Ore Reserves.
Forward-Looking Statements
The announcement carries standard forward-looking statement language, noting that references to feasibility studies, financial close, funding, production and permitting outcomes involve risks and uncertainties and may not eventuate.