Key Highlights

  • Mardie construction progress increased to 85%, from 69% a year earlier, with cumulative expenditure reaching $1.479 billion.
  • BCI crystallised 49,000 tonnes of salt during FY26, marking a key operational milestone as the project moves towards first commercial harvest.
  • Estimated construction expenditure required to complete Mardie fell to $258 million, compared with $508 million at the end of FY25.
  • Available funds stood at $423 million, while Debt drawn under the syndicated facilities reached $587 million at 30 June 2026.

BCI Minerals (ASX:BCI) shares are up 31.34% over the past year, trading at AUD 0.46, as the Mardie Salt and Potash Project moves closer to commercial production.

What's Driving the Stock

Construction completion at Mardie reached 85% at 30 June 2026, up from 69% a year earlier. The project produced its first crystallised salt during FY26, with 49,000 tonnes recorded by year-end as the brine circuit operated through the evaporation ponds and initial crystallisers.

Cumulative expenditure reached $1.479 billion, up from $1.113 billion, but the estimated cost still required to complete the project fell to $258 million from $508 million. The marine component reached 95% completion, with dredging underway and more than 30% of planned Volume excavated.

Funding Position

Total debt drawn under syndicated facilities reached $587 million, with available funding of $423 million. BCI holds three binding salt offtake agreements covering 62% of forecast production over the first three years, across China, Japan, Korea, Indonesia and Taiwan.

Is BCI Worth Watching?

FY27 priorities include the first salt harvest, completing dredging and marine works, and commissioning the salt wash plant. BCI's Total Recordable Injury Frequency Rate rose to 4.4 from 2.3, reflecting increased workforce and simultaneous construction and operational activity.