Key highlights

  • Kalina Power (ASX:KPO) reported progress on five secured Alberta projects.
  • The larger projects retained indicative in-service dates in 2029.
  • Kalina held AUD 11.4 million in cash and reported no Debt at 30 September.

Shares in Kalina Power (ASX:KPO) stood at AUD 0.014, a gain of 7.69% in the session at 11:52 a.m. AEDT on 20 November 2026. The S&P/ASX 200 benchmark was in negative territory during the session. The gas-fired power developer reported progress across its Alberta project portfolio and grid applications on 30 October 2026.

Alberta power projects advance through the queue

Kalina Power released its September-quarter report on 30 October 2026. It described work on five secured projects in Alberta and continued assessment of other sites. The portfolio comprises gas-fired facilities aimed at meeting Demand from large electricity users, including data centres. Kalina said its larger projects remained positioned for indicative in-service dates during 2029 under the Alberta Electric System Operator’s cluster process. The development work included grid applications, regulatory activity and engagement with potential users and other counterparties. The timetable comes from the status of the applications and remains subject to progress through the relevant processes.

Clairmont and the separate Saddle Hills application

The company elected to advance Clairmont in Cluster 2 and lodged approximately CAD 2.6 million in security with the system operator and ATCO. The remaining projects described in the queue section were in Cluster 3 and retained their original indicative dates in mid-2029. In addition, Kalina filed a Cluster 3 application for 100 megawatts at Saddle Hills. These applications refer to individual projects and their position in the grid connection process. Connection arrangements sit alongside other Due Diligence on each site, including discussions on gas Supply and engagement with financial and commercial counterparties. The cluster model groups applications into assessment rounds that use a common timetable for participants.

Changes to the federal assessment framework

Kalina reported that Canadian regulatory changes in September removed gas-fired power plants from the federal impact assessment list. It also discussed policy work at provincial and federal levels for large data centre developments. The company continued to follow Alberta’s work on a Large Load Allocation Process. The provincial connection and load allocation process is relevant to the timeline for customers seeking access to the power system. Kalina reported engagement with regulators, pipeline companies, gas producers, project financiers and prospective data centre customers as it progressed development across the Alberta portfolio.

Large electricity users and the Alberta market

Kalina’s report put data centre power applications in Alberta at more than 16 gigawatts during the quarter. That total describes demand in the application process. Individual projects still have to proceed through grid, siting and commercial arrangements. Kalina previously sold a 180-megawatt 2027 load allocation for CAD 18 million in late 2025. The sale was a separate transaction from the development programs in the latest report. Its portfolio now centres on generation projects being developed to meet new load applications, including users that require large and reliable electricity supply.

Funding and execution depend on several parties

At the end of September, Kalina reported about AUD 11.4 million in cash and no debt. Its development timelines depend on progress in the grid process, commercial agreements, access to fuel and project financing. The company reported ongoing discussions at several levels and described the larger projects’ 2029 positions as part of the connection queue. The queue position records progress in a defined regulatory process. Site works, procurement and operating readiness require later steps. For a project at this stage, a change in grid allocation or a proposed customer’s timing can affect the timetable.

In-service targets and commercial milestones

The next developments for the Alberta portfolio include progress in the cluster process, further definition of large-load allocation and commercial negotiations with counterparties. The company was also working on project readiness while pursuing additional sites. For individual plants, later disclosure could identify agreements with users, fuel suppliers, pipeline companies or funding partners and put those commitments against the corresponding site timetable. The larger projects’ indicative dates provide a framework for tracking development. The earlier sale of a load allocation is historical and the September portfolio involves separate delivery and connection work.

The Alberta portfolio today

Kalina’s projects are progressing through development and grid assessment. The timing of commercial arrangements and connection milestones will shape how each application advances.