  • Amplitude Energy Limited (ASX:AEL) advanced its East Coast Supply Project in Victoria.
  • The project reached a final Investment decision in September 2026.
  • The development targets up to 90 terajoules per day of gross gas production from 2028.
  • Expected FY27–FY28 development expenditure is A$190–210 million net to Amplitude.

Amplitude Energy Limited explores for, develops and produces Natural Gas in Australia, with operations and development interests focused on the Otway Basin and eastern domestic gas markets. Its shares (ASX:AEL) were quoted at AUD 1.648 on November 17, 2026, down 3.94% during the session. The company’s recent updates centred on the East Coast Supply Project, including a September final investment decision, development contracting and drilling results from the Juliet-1 well.

Otway Basin and Domestic Gas Operations

Amplitude’s East Coast Supply Project proposes to connect offshore gas resources in Victoria to existing infrastructure, including the Athena Gas Plant. Amplitude (ASX:AEL)'s brownfield character allows the company to consider using established gas-processing and pipeline Assets while still requiring offshore development work, safety assurance and regulatory compliance.

Amplitude (ASX:AEL) is operator and 50% interest holder in licence VIC/L24, with O.G. Energy holding the other 50%. The project is aimed at the Australian domestic market rather than international liquefied-natural-gas exports. Actual gas availability depends on reserves, drilling outcomes, processing capacity and the planned development schedule.

September Investment Decision and Nestor Well

On September 30, 2026, Amplitude announced a final investment decision to proceed with the development phase of the East Coast Supply Project. The plan targets gross production of up to 90 terajoules per day from 2028. That represents a project objective rather than gas already delivered into the market.

The company estimated point-forward development costs of A$190–210 million net to Amplitude across FY27 and FY28. It also sanctioned the Nestor exploration well, which could add resources if drilling results support a commercial discovery. Nestor is therefore separate from established development volumes and remains subject to exploration and appraisal uncertainty.

Juliet-1 Drilling Results and Technical Work

In September, the Juliet-1 well intersected the Waarre C reservoir and reached a total vertical depth below sea level of 2,299 metres. Preliminary measurements identified a gross gas-bearing interval of at least 60 metres, including 49 metres of interpreted high-quality net pay. These observations were consistent with the company’s initial assessment, but interpretation of logs is not identical to confirmed deliverable gas volumes.

Juliet-1 sits near the Casino, Henry and Netherby pipeline infrastructure. The well was subsequently completed, and Amplitude indicated that the Annie development well would follow. Integration of well test results, infrastructure engineering and the drilling schedule will matter in translating project studies into physical supply.

Financial Commitments, Risks and Timing

The announced A$190–210 million development-cost estimate is net to Amplitude and spans two financial years. It is distinct from the overall cost of operating existing assets and may change as delivery proceeds. Development activity will require equipment, offshore contractors and regulatory oversight. Unanticipated geological conditions, delays, cost changes and gas-market arrangements could influence timing and returns.

Investors following AEL (ASX:AEL) can monitor subsequent development expenditure, Nestor drilling, Annie well progress and the timing of connections to existing infrastructure. Gas volumes targeted for 2028 remain contingent on successful execution; they are not a current production figure.

Key Insights

Amplitude has moved the East Coast Supply Project from planning into a sanctioned development phase, with an indicated 2028 first-gas objective and sizeable net Capital commitments. Juliet-1 has provided further technical observations, while the Nestor exploration decision introduces additional uncertainty. Construction and drilling updates will be central to tracking AEL (ASX:AEL).