Key Highlights
- NEXTDC raised its FY27 net Revenue forecast to AUD 485 million to AUD 500 million on a constant currency basis.
- Underlying EBITDA guidance rose to AUD 260 million to AUD 275 million, compared with AUD 245 million to AUD 265 million in October.
- The upgraded Earnings ranges continue to exclude contributions from customer contracts affected by power delays at M3 Melbourne.
- NEXTDC retained FY27 Capital Expenditure guidance of AUD 4.5 billion to AUD 5 billion after a project-by-project review.
NEXTDC (ASX:NXT) designs, builds and operates data centres that provide customers with space, power and connectivity for computing equipment. In a 20 November 2026 update, it raised FY27 guidance for net revenue and underlying EBITDA and confirmed its capital expenditure range. The update followed a review that prioritised capital spending on delivering capacity already under contract.
Higher net revenue and underlying earnings
The November update raised the lower end of net revenue guidance by AUD 10 million and kept the upper end at AUD 500 million. NEXTDC defines net revenue as total revenue less direct costs. Management cited sales and revenue growth outside the affected M3 contracts and greater confidence in the timing of customer delivery. The new midpoint is 22% above FY26 net revenue of AUD 405 million.
The midpoint of underlying EBITDA guidance increased AUD 12.5 million. The company attributed the change primarily to cost savings from directing operating expenditure towards delivering customer capacity, as well as higher expected net revenue. The midpoint is 8% above FY26 underlying EBITDA of AUD 248.8 million.
Melbourne power delays and forecast scope
NEXTDC lowered earnings guidance on 21 October after power Supply delays at its M3 Melbourne site. The October and November forecasts exclude revenue and associated EBITDA from the affected contracts, including capacity already billing and any potential service level credits. Those contracts had accounted for approximately AUD 140 million of net revenue and AUD 140 million of underlying EBITDA in the August guidance.
NEXTDC said it could not yet reliably estimate the contracts' FY27 contribution and would provide an update once it could. The November forecast is on a constant currency basis. The company also excludes one-off costs linked to the M3 power delay from underlying EBITDA.
Capital spending and contracted projects
The capital spending range includes about AUD 500 million of reimbursable customer fitout and AUD 230 million of capitalised interest. Excluding interest, the range is approximately AUD 4.27 billion to AUD 4.77 billion. NEXTDC said this is about AUD 980 million below the August forecast on a comparable basis.
Most FY27 spending is directed to customer contracts at S4 Sydney, M2 and M3 Melbourne and KL1 Kuala Lumpur. At S4, 250 megawatts of the planned 365 megawatts of IT load were contracted and the first 115-megawatt phase was under construction. NEXTDC put several uncontracted development projects on hold and paused new land commitments.
NEXTDC said its October range already removed material discretionary spending from the year. The remaining program focuses on contracted capacity due within 12 to 18 months and work already close to completion. For new investment, the company said it would assess projects individually, considering customer contracts, expected returns above its capital cost, access to power, the status of planning and the availability of funding before committing capital.
What to watch as capacity is handed over
NEXTDC plans to complete construction, hand over capacity and start billing under customer contracts. It continues to evaluate a possible joint venture for S4 Sydney. The timing of delivery and NEXTDC's ability to estimate the contribution of the affected M3 contracts remain distinct milestones for forthcoming updates.