Highlights
- NEXTDC (ASX:NXT) reported FY26 net Revenue of A$405.0 million, up 16%, and underlying EBITDA of A$248.8 million, up 15%.
- Pro forma contracted utilisation reached 740.1MW, compared with 244.8MW a year earlier.
- Billing utilisation was 175.0MW and the pro forma forward order book was 565.1MW.
- FY27 guidance is net revenue of A$615 million to A$640 million and Capital Expenditure of A$5,250 million to A$5,750 million.
- Pro forma Liquidity was A$8,676 million.
NEXTDC (ASX:NXT) is a Data Centre-as-a-Service provider with Tier IV facilities in Australia and a growing presence in Asia. Its Cloud Centre ecosystem connects carriers, cloud providers and IT service providers. The company's FY26 results, released on 27 August 2026, combine strong contracting activity with a substantially larger development and funding program.
FY26 Financial Results
Net revenue was A$405.0 million compared with A$350.2 million in FY25, above the A$390 million to A$400 million guidance. Underlying EBITDA was A$248.8 million, above guidance of A$230 million to A$240 million. Statutory net profit after tax was A$82.1 million, against a A$60.5 million loss a year earlier, and this includes a A$128.8 million Fair Value gain on two Investment properties. On the historical accounting basis NEXTDC (ASX:NXT) calculated a FY26 loss after tax of A$103.9 million (unaudited). Capital expenditure was A$3,397 million, above the A$2,700 million to A$3,000 million guidance after several upward revisions that the company attributed to accelerated construction and land Acquisition timing.
Contracted Capacity and Development Projects
At 30 June 2026 pro forma contracted utilisation was 740.1MW, billing utilisation was 175.0MW and built capacity was 287.9MW, including 80.0MW added during FY26. The pro forma forward order book of 565.1MW includes only binding contracts, and management estimates contracted EBITDA from existing contracts will exceed A$1.0 billion, a forward-looking estimate. Projects include S4 Sydney, with 250MW in progress and 115MW in planning, M3 Melbourne with 165MW in progress, and planning for up to 1.2GW at M5 Melbourne. In Asia, KL1 Kuala Lumpur opened to its foundation customer in May 2026, and excavation has begun at TK1 Tokyo.
Funding and FY27 Guidance
Pro forma liquidity was A$8,676 million, comprising A$876 million of cash, A$4,800 million of undrawn senior debt, a further A$2,300 million of senior Debt that reached financial close on 15 July 2026, and a A$700 million hybrid securities delayed draw. NEXTDC (ASX:NXT) has raised A$9.75 billion since August 2025 across senior debt, subordinated notes, hybrid securities and equity. FY27 guidance, in constant currency, is net revenue of A$615 million to A$640 million and underlying EBITDA of A$385 million to A$410 million. It assumes 197MW converts to billing during FY27.
Grid Reform and Execution Risks
New South Wales and Commonwealth governments are proposing reforms to data centre grid connections and energy use, and the company states its operating portfolio and 565MW order book are unaffected. Transgrid confirmed in writing that its new capacity allocation policy does not apply to S4 Sydney. Nonetheless, NEXTDC (ASX:NXT) identified regulatory change, delivery of up to A$5,750 million of FY27 capital expenditure and conversion of contracted capacity as risks. Management also stated there is no assurance that all contracts will complete within the expected timeframe or at all.
Key Insights
NEXTDC (ASX:NXT) delivered FY26 results above its guidance ranges while contracted capacity more than tripled on a pro forma basis. The conversion of that capacity into billing, delivery of a large capital program and the outcome of grid-connection reforms remain the main uncertainties.