Highlights
- DigiCo Infrastructure REIT (ASX:DGT) outlined its Australian development priorities at the annual meeting on 11 November 2026.
- The Sydney project’s 88MW of capacity was fully contracted, following a 71MW customer agreement.
- The next 52MW expansion is scheduled for delivery across FY27 and FY28 under management’s development timetable.
- The November presentation outlined approximately AUD 1.2 billion in pro forma liquidity, including anticipated US asset sale proceeds.
DigiCo Infrastructure REIT (ASX:DGT) invests in, develops and operates data centres serving digital infrastructure customers across Australia and North America. On 24 November 2026, its securities traded at AUD 2.375, down 0.21% for the session. The November annual meeting outlined the group’s Sydney capacity expansion and associated Capital management priorities.
Sydney Capacity Expansion and Customer Contracting
The SYD1 development is the principal project in DigiCo’s current Australian expansion programme. Management reported at the November annual meeting that the initial 20MW project had been delivered within its scheduled timeframe and budget. A further 52MW is being developed through the reuse of existing infrastructure. The project has secured planning approval and access to power and water, according to the presentation. The customer agreement announced in October covers 71MW and has a 15-year term. Contracted capacity establishes future customer commitments but does not mean that all capacity is already operational or generating revenue.
Adelaide Expansion and Australian Development Strategy
Alongside Sydney, DigiCo is progressing a proposed 15MW expansion at its ADL1 Facility in Adelaide, compared with an earlier plan for 8MW. The November presentation described customer negotiations as advanced, rather than identifying the additional capacity as fully leased. The group is also assessing undeveloped sites for potential campus-style facilities. These projects represent different stages of capital commitment and technical preparation. Access to electricity, water and network connectivity is particularly relevant when evaluating locations capable of supporting intensive computing workloads.
FY26 Earnings and Capital Redeployment
Underlying earnings before interest, tax, Depreciation and Amortisation reached AUD 127 million in the year ended 30 June 2026, exceeding the AUD 125 million guidance. Annual distributions declared amounted to 12 cents per security, consistent with guidance. Management’s November presentation linked the sale of US Assets with the funding strategy for Australian developments. Its pro forma estimates indicated net Debt of approximately AUD 500 million and gearing of 18%, compared with AUD 1.6 billion and 39% respectively at June 2026. These estimates incorporate anticipated net proceeds, transaction adjustments and an assumed exchange rate; they are not a subsequent audited balance sheet.
Construction, Power and Customer Risks
Delivering new data centre capacity requires coordination across construction, electrical installation and commissioning. Delays in preparing individual data halls could alter the timing of customer occupation and associated receipts. A fixed-price design and construction arrangement for the Sydney expansion addresses part of the construction cost exposure, but does not eliminate execution risk. Large customer contracts also make counterparty performance and contractual delivery requirements important considerations. Power consumption, equipment availability and financing costs remain relevant to the Economics of operating and developing facilities.
What to Watch Next
Management targets the first 10MW of the 52MW Sydney expansion to become operational late in the fourth quarter of FY27. Remaining capacity is planned for progressive delivery during FY28, with completion of the overall project targeted by that financial year-end. Future updates may clarify progress on structural works and energisation, alongside customer contracting at Adelaide. Actual Liquidity and gearing following asset disposals will provide further context for assessing the development funding plan.
Key Insights
DigiCo’s November disclosures show a shift in capital deployment towards Australian data centre capacity. The Sydney contract provides a commercial framework for development, while physical delivery remains a separate requirement. Construction milestones, realised disposal proceeds and the timing of income generation are central to assessing the transition from contracted capacity to operating assets.