Key Highlights
- Second-quarter 2026 Revenue from the legacy hosting Business was USD 2.915 million, with a net loss of USD 3.481 million.
- Cash was USD 52.8 million at 30 June 2026, largely from a June 2026 public offering raising about USD 59 million net.
- An October presentation cites about 120 megawatts of contracted Utility power, including 65 megawatts at CLT1, with first halls expected in the fourth quarter of 2027.
From hosting Bitcoin miners to AI capacity
AIB Data Centers Inc. (NYSE American:AIB) is a relatively young company in the middle of a change of strategy. It was previously named BlockchAIn Digital Infrastructure, Inc., and changed its name on 25 June 2026. Its shares began trading as AIB on 17 March 2026, following a business combination with Signing Day Sports that closed on 16 March.
The company now describes itself as a developer, owner and operator of 40 to 90 megawatt data centres for artificial intelligence and high-performance computing, built on contracted power. On 5 June 2026 it de-energised substantially all of its legacy Bitcoin Mining hosting operations in order to redeploy power, and management expects revenue from that business to fall significantly from the third quarter.
Second-quarter figures
The latest reported results cover the quarter ended 30 June 2026, filed on Form 10-Q on 13 August 2026. They reflect only the legacy hosting business. Revenue was USD 2.915 million against USD 4.745 million a year earlier. The company swung to a gross loss of USD 0.517 million from a Gross Profit of USD 0.549 million. The net loss was USD 3.481 million, or USD 0.07 per share, against a loss of USD 0.542 million, and adjusted EBITDA was a loss of USD 3.073 million.
Cash was USD 52.8 million at 30 June 2026, against USD 15,000 at the end of 2025, largely from a June 2026 public offering raising about USD 59 million net. Total Assets rose to USD 90.4 million from USD 17.3 million. The company reported no traditional debt. After quarter end, it paid about USD 11.2 million in cash for a Texas acquisition, with a USD 6.0 million deferred balance secured by a standby letter of credit. The presentation cites 15 megawatts energised in Texas at closing and 40 megawatts contracted but not yet energised. Two customers accounted for substantially all revenue, and shares outstanding were 75,979,466.
The October investor presentation
A presentation filed on 20 October 2026 sets out the new plan. It cites about 120 megawatts of contracted utility power across the portfolio, including 65 megawatts at a site called CLT1 under a 15-year agreement signed in May 2026. A customer agreement covers 50 megawatts of critical IT capacity at CLT1 for an initial 12 years. The company says first halls are expected in the fourth quarter of 2027, but describes that as an estimate and not a target or guidance.
Four other sites are at earlier stages. The company has not entered into customer agreements for them, and three have no executed utility agreement. The presentation also gives illustrative contract-value projections of about USD 6.56 billion for those sites, which are unaudited and expressly not guidance.
Financing has not been completed. The company intends to rely on customer prepayments, project-level Debt and project-level preferred equity, and chief executive Jerry Tang wrote on 7 October 2026 that it does not currently anticipate needing corporate-level common Equity for CLT1. Availability and terms of project financing are not assured.
What to watch
Key questions include whether the company completes project financing, whether further customer agreements follow, whether utility agreements are executed for the remaining sites, and how quickly legacy revenue declines before AI revenue begins.