Key Highlights

  • FY26 underlying EBITDA was AUD 127 million, exceeding the company’s AUD 125 million guidance.
  • DigiCo reported letters of intent for 52 MW of remaining capacity at SYD1 and pro-forma Liquidity of approximately AUD 1.2 billion.
  • This article reviews capacity delivery, asset sales, Debt and execution risks.

DigiCo Infrastructure REIT (ASX:DGT) owns and develops data-centre infrastructure with a focus on Australian capacity expansion. Its FY26 presentation reported underlying EBITDA of AUD 127 million, above the AUD 125 million guidance level, and declared distributions of 12.0 Australian cents per security. The trust highlighted completion of the initial 20 MW at its SYD1 development on time and on budget. These operational measures are important because data-centre financial outcomes are linked not only to owning capacity but also to the timing of development, customer contracts and Revenue commencement.

What Is the Capacity Pipeline?

The company announced letters of intent covering the remaining 52 MW at SYD1, subject to binding documentation. It planned delivery of this expansion across FY27 and FY28, while evaluating approximately 15 MW of expansion at its Adelaide facility. Letters of intent are not equivalent to completed leases or revenue-producing customer capacity, so contracted terms and construction progress need to be tracked separately. Building additional powered capacity can expand the platform, but requires large upfront Investment and careful management of procurement, technical delivery and customer commissioning.

What Changed in the Capital Structure?

DigiCo outlined the disposal of selected US data-centre Assets as part of a strategy to concentrate capital on Australia. The presentation projected net debt declining from approximately AUD 1.6 billion to AUD 0.5 billion on a pro-forma basis, and gearing moving from 39% to about 18%, subject to transaction assumptions and completion adjustments. Pro-forma liquidity of AUD 1.2 billion was also disclosed. The company stated that its planned SYD1 expansion was fully funded without new Equity under the assumptions presented. These are planning metrics, not completed-period audited balances.

How Is Future Earnings Capacity Measured?

Management provided an estimate of approximately AUD 250 million in annualised stabilised EBITDA for its Australian platform once planned capacity at SYD1 and Adelaide was occupied and billing. That figure is not current FY26 earnings and depends on successful project delivery, customer take-up and operational stabilisation. It should therefore be evaluated separately from the reported AUD 127 million of FY26 underlying EBITDA. Future reporting can test progress by measuring installed capacity, binding contracts, commissioned load, operating costs and how quickly newly delivered megawatts begin generating rental or service revenue.

What Are the Execution Risks?

Funding availability, grid access, cooling capability, construction costs and customer concentration matter in data-centre expansion. The difference between a signed letter of intent and a binding agreement is especially relevant when assessing pipeline conversion. Higher utilisation can lift earnings, but projects may generate financing and development costs before stabilising. DigiCo’s FY26 figures show operational delivery and financing plans; they do not eliminate uncertainty around future capacity rollout. Investors can monitor the timing of Australian asset expansions, the completion of announced disposals and the evolution of debt and liquidity.

Key Insights

DigiCo Infrastructure REIT (ASX:DGT) presents a combination of measurable 2026 operating developments and risks that differ from other real estate businesses. The reported results provide a factual baseline for assessing management execution, financial flexibility and future commitments. Subsequent disclosures will show whether projects, leasing or operating initiatives translate into repeatable earnings and cash flow. Reported forecasts and indicative plans should be distinguished from achieved financial outcomes.