Key Highlights

  • Havilah Resources Limited (ASX:HAV) has released to the ASX the Kalkaroo Copper-Gold Project Site Visit Presentation prepared by Sandfire Resources (ASX:SFR), on Wednesday 25 November 2026.
  • Havilah is the current owner of Kalkaroo in South Australia, and Sandfire holds an exclusive right to acquire 80% of the project.
  • The presentation was prepared for a financial community site visit to Kalkaroo on Wednesday 25 November 2026.
  • Kalkaroo is in north-eastern South Australia, about 90km west-northwest of Broken Hill and about 500km northeast of Adelaide.

Havilah Resources Limited (ASX:HAV) has released to the ASX the Kalkaroo Copper-Gold Project Site Visit Presentation prepared by Sandfire Resources (ASX:SFR), on Wednesday 25 November 2026.

The "SFR:" prefix in the headline shows the document is Sandfire's. Havilah is the current owner of Kalkaroo in South Australia, and Sandfire holds an exclusive right to acquire 80% of the project. That makes the presentation directly relevant to Havilah shareholders.

What did Havilah announce?

The presentation was prepared for a financial community site visit to Kalkaroo on Wednesday 25 November 2026. It was released under the authority of CEO and Managing Director Brendan Harris.

Location and access. Kalkaroo is in north-eastern South Australia, about 90km west-northwest of Broken Hill and about 500km northeast of Adelaide. The presentation says the Barrier Highway is about 50km by existing road, and a proposed rail siding on the existing railway is about 75km away, with rail links to Port Pirie, Whyalla and Port Adelaide. Power would notionally need a roughly 100km, 220kV line to Broken Hill.

Ownership. Sandfire holds an exclusive right to acquire an 80% interest in Kalkaroo from Havilah Resources (ASX:HAV). It has paid A$105 million upfront to secure that right, with a further A$105 million payable to complete the acquisition. Havilah keeps a 20% interest, free-carried to a final investment decision (FID), and Sandfire has a right of first refusal over that 20%.

Resources and reserves. The presentation reproduces Havilah's 2018 estimates: a sulphide Mineral Resource of 224Mt at 0.49% copper and 0.36g/t gold, and an Ore Reserve of 100Mt at 0.47% copper and 0.44g/t gold. Sandfire states it is not aware of new information that materially affects these estimates.

Study and drilling. A pre-feasibility study (PFS) is under way, targeted for completion in H2 FY28. Annual throughput of 10–20Mt is being assessed. Six rigs (four diamond, two RC) are on site with an 80-person camp, as part of about 130km of infill and extension drilling. The company reported 8.7km drilled in Q1 FY27 and a further 6.5km in October, with drilling expected to finish in H1 FY28. No new assay results were presented. FY27 guidance shows US$51 million of Kalkaroo PFS costs, expected to be capitalised.

Approvals. South Australian PEPR and federal EPBC approvals are identified as the critical path to FID, with at least two years of baseline surveys needed.

Regional exploration. Through a strategic alliance with Havilah covering 8,847km² of tenure, Sandfire is funding A$30 million over two years, and can earn 80% of any discovery by sole-funding to a maiden Mineral Resource.

Chief Operating Officer Jason Grace described the staged entry as offering "a low-cost, copper-gold growth option with material asymmetric upside for the company's shareholders."

Upcoming Developments

Assay results from the current drilling program, which the presentation says are pending.

Progress towards the A$105 million completion payment for the 80% interest.

The PFS, targeted for H2 FY28, and any updated Mineral Resource.

Approvals progress under the PEPR and EPBC processes.

Results from regional alliance drilling at targets such as Eurinilla Dome and Homestead.

Related Sector Context

Mineral exploration and development depend on geological confidence, Commodity Demand and access to capital. Exploration results and technical studies help establish project priorities, but commercial viability also depends on recoveries, infrastructure, permitting and development costs.

Site visit presentations often consolidate previously disclosed information, and Sandfire explicitly says the resource and reserve figures have not materially changed. The items that may interest investors are the operational details: drilling rates, rig numbers, the 10–20Mt throughput range under study and the timeline to PFS.

The resource and reserve figures date from 2018 and were prepared by Havilah. Updated estimates using Sandfire's new drilling and geological modelling could, in time, differ from the current figures, either up or down.

The presentation also restates Sandfire's group position: net cash of US$342 million and an undrawn Facility of US$650 million at September 2026, and unchanged FY27 group guidance. That context may help investors judge how the project sits alongside Sandfire's existing operations.

The environmental issues flagged, including protected species (the Plains Wanderer and Purple-wood Wattle) and the need to divert an ephemeral creek, are the kind of matters that can affect approval timing.

Risks to Watch Out

Exploration and development outcomes depend on geological continuity, technical studies and access to funding. Reported exploration results do not necessarily establish economically recoverable resources. Changes in commodity prices, Capital expenditure, permitting or project schedules could affect the feasibility and timing of future activities.