Key Highlights

  • Sandfire Resources Limited (ASX:SFR) has released a 37-page presentation for an investor and analyst site visit to the Kalkaroo copper-gold project in South Australia, held on Wednesday 25 November 2026.
  • It has paid A$105 million upfront to secure that right, with a further A$105 million payable to complete the acquisition.
  • Six rigs (four diamond, two RC) are on site with an 80-person camp, as part of about 130km of infill and extension drilling.
  • The company reported 8.7km drilled in Q1 FY27 and a further 6.5km in October, with drilling expected to finish in H1 FY28.

Sandfire Resources Limited (ASX:SFR) has released a 37-page presentation for an investor and analyst site visit to the Kalkaroo copper-gold project in South Australia, held on Wednesday 25 November 2026.

The copper producer is working towards acquiring 80% of Kalkaroo from Havilah Resources. The presentation sets out drilling progress, study timelines and approval pathways, alongside reconfirmed resource and reserve figures. The presentation gives one of the more detailed public pictures of how Sandfire is approaching the project.

What did Sandfire announce?

The presentation was prepared for a financial community site visit to Kalkaroo on Wednesday 25 November 2026. It was released under the authority of CEO and Managing Director Brendan Harris.

Location and access. Kalkaroo is in north-eastern South Australia, about 90km west-northwest of Broken Hill and about 500km northeast of Adelaide. The presentation says the Barrier Highway is about 50km by existing road, and a proposed rail siding on the existing railway is about 75km away, with rail links to Port Pirie, Whyalla and Port Adelaide. Power would notionally need a roughly 100km, 220kV line to Broken Hill.

Ownership. Sandfire holds an exclusive right to acquire an 80% interest in Kalkaroo from Havilah Resources (ASX:HAV). It has paid A$105 million upfront to secure that right, with a further A$105 million payable to complete the acquisition. Havilah keeps a 20% interest, free-carried to a final investment decision (FID), and Sandfire has a right of first refusal over that 20%.

Resources and reserves. The presentation reproduces Havilah's 2018 estimates: a sulphide Mineral Resource of 224Mt at 0.49% copper and 0.36g/t gold, and an Ore Reserve of 100Mt at 0.47% copper and 0.44g/t gold. Sandfire states it is not aware of new information that materially affects these estimates.

Study and drilling. A pre-feasibility study (PFS) is under way, targeted for completion in H2 FY28. Annual throughput of 10–20Mt is being assessed. Six rigs (four diamond, two RC) are on site with an 80-person camp, as part of about 130km of infill and extension drilling. The company reported 8.7km drilled in Q1 FY27 and a further 6.5km in October, with drilling expected to finish in H1 FY28. No new assay results were presented. FY27 guidance shows US$51 million of Kalkaroo PFS costs, expected to be capitalised.

Approvals. South Australian PEPR and federal EPBC approvals are identified as the critical path to FID, with at least two years of baseline surveys needed.

Regional exploration. Through a strategic alliance with Havilah covering 8,847km² of tenure, Sandfire is funding A$30 million over two years, and can earn 80% of any discovery by sole-funding to a maiden Mineral Resource.

Chief Operating Officer Jason Grace described the staged entry as offering a low-cost, copper-gold growth option with material asymmetric upside for the company’s shareholders.

Related Sector Context

Mineral exploration and Mining involve successive stages of geological assessment, resource definition, feasibility work and development. Commodity demand, grade, recovery, infrastructure and access to Capital shape the Economics of projects. Exploration results alone do not establish a commercially viable operation.

Risks to Watch Out

Project economics may change as further geological information becomes available and as assumptions for recovery, operating expenditure and capital requirements are refined. Commodity prices and access to funding can influence development decisions. Delays in technical studies, approvals or contractor availability could increase expenditure before a project generates revenue.

Geological continuity and resource classification may change with further drilling. Development schedules are also exposed to permitting, contractor availability and cost escalation. Additional Equity or Debt funding could be required before production, and potential Revenue remains sensitive to commodity prices and realised recoveries.

What should investors watch next?

Assay results from the current drilling program, which the presentation says are pending.

Progress towards the A$105 million completion payment for the 80% interest.

The PFS, targeted for H2 FY28, and any updated Mineral Resource.

Approvals progress under the PEPR and EPBC processes.

Results from regional alliance drilling at targets such as Eurinilla Dome and Homestead.