Highlights
- Stelar Metals (ASX:SLB) has completed its first drilling programme at the Hill of Leaders tungsten project in the Northern Territory.
- Drilling covered 26 reverse circulation holes, about 3,300 metres, across four prospects.
- Scheelite was logged in every hole by ultraviolet fluorescence, though these are visual observations and not assays.
- A maiden soil survey of about 50 square kilometres reported anomalies that expanded the footprint at least two-fold.
- Laboratory assays from ALS in Adelaide are the next milestone.
Stelar Metals (ASX:SLB) is an Australian explorer focused on the Hill of Leaders tungsten project, which covers roughly 445 square kilometres in the Tennant Creek region of the Northern Territory. The company has finished its first drilling programme at the project and is waiting for laboratory results that will test what the drill chips showed visually.
Drilling Results So Far
Drilling began on 13 October 2026. By 9 November Stelar Metals (ASX:SLB) had completed 26 reverse circulation holes for roughly 3,300 metres across four prospects: Hill of Leaders, Doria, Curtis and Makinsons. Scheelite, a tungsten mineral, fluoresced under ultraviolet light to some degree in every hole, and visual estimates included 1% to 5% scheelite over three metres to four metres in individual holes. Wolframite was also logged. The company cautioned that the drill spacing does not establish continuity.
Soil Survey Update
On 18 November the company reported preliminary results from a maiden soil survey covering about 50 square kilometres with roughly 1,350 samples. It described multiple coherent anomalies in which tungsten sits alongside pathfinder elements such as tin, bismuth and molybdenum, and said the known mineralised footprint had expanded at least two-fold along strike. The readings came from a portable XRF instrument, which the company noted may have detection limits too high for tungsten alone. That release also confirmed that the maiden drilling programme was complete.
Project Background and Funding
Stelar Metals (ASX:SLB) acquired its interest in Hill of Leaders in May 2026 under an earn-in agreement with F&H Brothers Metals, which gives it an option to take 100% of the project. Tungsten was first discovered in the area in 1951, but this year's programme was the first to test the system at depth. Surface sampling earlier in the year returned grades of up to 15.69% WO3. In August the company raised about $2.6 million through a Placement to fund the work.
Next Steps and Risks
The next milestone is the release of the first assays from ALS in Adelaide, and the company has said further Reverse Circulation Drilling is planned, with diamond drilling possible if results warrant. Stelar Metals (ASX:SLB) has no mineral resource, visual estimates may not be borne out by assays, and the project is held under an earn-in. Tungsten is used in hard metals, defence and electronics, and the company has pointed to Chinese export controls as supportive of Western projects.
Key Insights
Stelar Metals (ASX:SLB) has completed its first drilling at Hill of Leaders, with visual scheelite in every hole and a soil footprint that expanded along strike, but none of this is confirmed by assays yet. The laboratory results and any follow-up drilling will determine whether the visual observations translate into measured tungsten grades.






Please wait processing your request...