Highlights
- Touquoy began processing stockpiled ore on 3 November 2026.
- FY27 Touquoy production guidance is 17,000–21,000 ounces of gold.
- FY27 All-In Sustaining Cost guidance is AUD 2,070–2,560 per ounce.
- Nova Scotia growth Capital guidance is AUD 40–50 million for FY27.
St Barbara Limited (ASX:SBM) develops and operates gold assets, with its 2026 activity centred on Nova Scotia in Canada and arrangements involving the Simberi operation in Papua New Guinea. Its shares closed at AUD 0.805 on 5 November 2026. The company announced on the same date that ore processing had begun at the Touquoy Restart Project on 3 November, following preparations to bring stockpiled material through the existing plant. The operational restart gives greater definition to its FY27 production and expenditure plans while development work continues around the proposed 15-Mile Processing Hub.
Touquoy Processing Restart
St Barbara reported that the first ore passed through the Touquoy ball mill on 3 November 2026. The restart is processing remaining low- and medium-grade stockpiles rather than representing the commencement of a newly mined orebody. This distinction matters when assessing the scale and duration of the activity. The company expects commissioning to progress toward full processing capacity by the end of December 2026, with first gold doré production anticipated in January 2027. Those are scheduled outcomes, rather than production already achieved. The company also expects the recommencement to support approximately 200 jobs in Nova Scotia. For St Barbara (ASX:SBM), the immediate operational indicators will be plant availability, throughput and recovery as the ramp-up develops.
FY27 Guidance and Capital Requirements
The 5 November release established FY27 Touquoy gold production guidance of 17,000–21,000 ounces and an all-in sustaining cost range of AUD 2,070–2,560 per ounce. Guidance covers an anticipated reporting outcome, not a confirmed production result. St Barbara (ASX:SBM) also guided to AUD 40–50 million of growth capital across Touquoy and the 15-Mile Processing Hub, subject to permitting timetables. Touquoy reclamation expenditure is expected to total AUD 24–30 million, while exploration spending is forecast at AUD 6–7 million. Each allocation has a different purpose: restarting processing, preparing future infrastructure, rehabilitating the existing site and testing potential future mineral inventory. Consequently, investors assessing the capital programme need to consider both the expected output and the cash required to execute it.
Nova Scotia Development and Portfolio Changes
Beyond the restart, St Barbara progressed its 15-Mile Processing Hub work during 2026, including an updated pre-feasibility study released in September. Its Nova Scotia exploration programme and November update on a maiden underground resource at Old Austen are additional inputs into future planning. Mineral resources are estimates of geological inventory; they should not be treated as ore already scheduled for profitable extraction. During September the company also announced an agreement to sell its Simberi interest, marking a proposed shift in portfolio emphasis. The terms and completion status of any transaction must be considered independently of the operating guidance for Touquoy. For St Barbara (ASX:SBM), the common Factor linking these activities is the allocation of management time and capital among existing processing, project evaluation and longer-term development.
Execution Risks and Key Insights
Near-term results depend on commissioning performance, actual grades and recoveries from stockpiles, operating expenditure and timing of doré sales. The 15-Mile timetable remains dependent on regulatory and development progress. Reclamation work introduces a further spending requirement, and the company said reclamation bond releases were not anticipated in FY27 because inspection and sign-off would follow completed work. St Barbara (ASX:SBM) therefore enters the next reporting periods with identifiable milestones but material execution tasks still ahead. Key Insights: the start of processing is a completed 2026 event, while FY27 ounces, sustaining costs and future capital requirements remain company guidance. Subsequent quarterly reports should clarify how production, spending and permitting compare with those plans.