Highlights
- Exploitation permits were granted for Bankan and Mansounia by decree dated 16 November 2026.
- Each permit carries a 15-year term.
- Bankan has a Probable Ore Reserve of 51.6 Mt at 1.78 g/t gold for 2.95 million ounces.
- First gold at Bankan is expected in mid-2028.
- The Government of Guinea is entitled to a 15% interest under the Mining Code.
PDI Gold Limited (ASX:PDI) operates the Kiniéro Gold Mine in Guinea and is developing the Bankan project. On 17 November 2026 it reported that industrial mining exploitation permits had been granted for Bankan and for the Mansounia deposit at Kiniéro under Presidential Decrees dated 16 November 2026.
The Permits
The Bankan permit, held by Hamana Gold SA, covers 98.6 square kilometres for a 15-year term. Two Mansounia permits, held by Sycamore Mine Guinée SAU, also carry 15-year terms, one covering 44.7 square kilometres. Under the Guinea Mining Code, the Government of Guinea is entitled to a 15% interest. Managing Director and Chief Executive Matthew Wilcox described the grant as a key milestone for PDI Gold (ASX:PDI).
The permits remove a significant approval hurdle, but the government's 15% entitlement will affect the share of project value attributable to PDI shareholders.
What Bankan Holds
Bankan, where the NEB and BC deposits were discovered in 2020, carries a Probable Ore Reserve of 51.6 million tonnes at 1.78 g/t gold for 2.95 million ounces. Its Indicated Mineral Resource is 83.7 million tonnes at 1.54 g/t for 4.14 million ounces, with a further Inferred Resource of 16.8 million tonnes at 2.28 g/t for 1.23 million ounces.
The June 2025 Definitive Feasibility Study outlined production of 250,000 ounces a year over a 12-year mine life, a Capital cost of US$463 million and an All-In Sustaining Cost of US$1,111 an ounce at a gold price of US$3,300 an ounce. PDI (ASX:PDI) says it does not expect the capital estimate to rise and is pursuing initiatives to reduce it. These are study forecasts, not achieved results.
Mansounia and the Operating Base
Mansounia has a Probable Ore Reserve of 19.5 million tonnes at 0.77 g/t gold for 480,000 ounces. The deposit is near-surface with a low strip ratio, grade control drilling and initial pit stage designs are complete, and mining preparation starts immediately.
That work builds on Kiniéro, which poured first gold in December 2025 and reached commercial production in February 2026. The plant has a nameplate capacity of 6 million tonnes a year, which the company says it is consistently exceeding. Guidance for 2026 is 157,000 to 174,000 ounces poured at an all-in sustaining cost of US$1,100 to US$1,300 an ounce. At 31 October 2026, 662 Guinean nationals were employed directly and 1,417 more through local contractors.
From Permit to Construction
PDI Gold (ASX:PDI) says construction at Bankan will begin as soon as practicable, following accelerated procurement, detailed engineering and compensation work. Down payments totalling US$18 million have already been made for the SAG and ball mills and a 40-megawatt power station. First gold is expected in mid-2028, and an optimised schedule, capital cost estimate and production profile are due in early 2027.
The announcement did not describe an overall financing package for the US$463 million build or report net present value, internal rate of return or payback figures. The capital cost and the mid-2028 target could change once the optimised plan is released, and production and cost figures come from company studies. The company expects about 2,000 jobs during construction and about 1,000 ongoing operating roles.
Key Insights
PDI Gold (ASX:PDI) has secured 15-year exploitation permits for Bankan and Mansounia. Financing, the optimised plan due in early 2027 and the mid-2028 first gold target remain to be delivered.