Highlights
- Ora Banda produced 33,305 ounces of gold in the September 2026 quarter, including attributable third-party ounces.
- Quarterly gold sales were 33,939 ounces at an All-In Sustaining Cost of AUD 4,214 per ounce sold.
- Cash at 30 September 2026 totalled AUD 207.0 million.
- Ora Banda (ASX:OBM) started construction of a new 3.0-million-tonne-a-year processing plant.
Ora Banda Mining Limited (ASX:OBM) produces gold in Western Australia through its Davyhurst operations, supported by underground mines, a processing plant and exploration across its surrounding tenements. Its September 2026 quarterly update documented a period of production disruption alongside substantial development spending. Shares ended the 5 November 2026 Trading session at AUD 1.475, based on the supplied price. The operational significance of the quarter lies in the balance between current output and construction work intended to change the processing configuration over time.
September Quarter Gold Output and Costs
Ora Banda reported 33,305 ounces of gold produced in the three months ended 30 September 2026, including 11,609 attributable equivalent ounces from third-party processing. Gold sold totalled 33,939 ounces. The reported all-in sustaining cost was AUD 4,214 per ounce sold. The company attributed the higher unit cost to wet weather affecting haulage and an extended shutdown at its existing mill for maintenance and a gearbox replacement. Throughput at the Davyhurst mill fell 17% against the June quarter, with 271,879 tonnes milled at a head grade of 2.7 grams per tonne.
Underground Development and Plant Construction
Ora Banda (ASX:OBM) commenced underground development at Waihi during the September quarter. The company expects high-grade ore from this operation from mid-calendar 2027, although future timing is subject to development progress. It also began construction of a new processing plant designed for 3.0 million tonnes per annum. At the reporting date, works included earthworks, foundations and structural activity; the company said critical long-lead items had been sourced or ordered. Riverina was meanwhile operating with a single jumbo after the second jumbo was transferred to Waihi. None of these planned contributions is equivalent to current-quarter gold output.
Cash Position, Capital Expenditure and Outlook
At 30 September 2026, Ora Banda held AUD 207.0 million in cash. Quarterly Operating Cash Flow was AUD 83.3 million, while expenditure on exploration, development and growth projects reached AUD 133.7 million. Subsequent to quarter-end, its revolving Credit Facility was increased to AUD 300 million, bringing stated Liquidity to AUD 507 million when combined with quarter-end cash. Ora Banda maintained its FY27 guidance despite the quarter's operational interruption. Its 'DRIVE to 300' name refers to an aspiration, not a formal production target; the company explicitly states that it does not yet have reasonable grounds to believe that aspiration can be achieved.
Exploration and Execution Risks
The Davyhurst development strategy relies on the timing of underground access, mine development, plant construction and the availability of suitable ore feed. Wet-weather disruptions and mill downtime demonstrate how operational constraints can affect throughput and reported unit costs. Gold prices can influence revenue, while rising development spending creates demands on cash and available facilities. Ora Banda (ASX:OBM) reported drilling around Little Gem, where the company anticipated a maiden mineral resource later in FY27. That remains a planned estimate, and exploration intercepts should not be presented as established reserves. Subsequent updates on plant progress, mine access, processing recoveries and the composition of cash flow will provide more concrete evidence of execution.
Key Insights
Ora Banda Mining (ASX:OBM) reported lower Davyhurst processing activity during the September 2026 quarter while advancing Waihi underground and its new processing plant. Gold production, the AUD 207.0 million cash balance and higher project spending give a measurable view of the business. Construction milestones and future quarterly cost outcomes will help assess the transition from current operations to a different processing scale.