Key Highlights
- Three drill holes completed for 939.5m within the Etayo Investigation Permit in northern Spain
- Phase 1 results at Mina Emilia included 0.55m at 0.84% Cu and 11g/t Ag from 75.05m in hole ET-01
- Combined downhole-surface IP surveys identified coherent near-surface chargeability anomalies at ET-04
- Phase 2 drilling proposal submitted to provincial administration, with approval expected within 1-2 months
Megado Minerals Limited (ASX:MEG) has reported progress at the Iberian Copper Project (IBC) in the regions of Navarra and Aragon in northern Spain, including final assay results from Phase 1 drilling and the submission of a Phase 2 drilling proposal. The IBC occurs within a broad sedimentary sequence where mineralisation is associated with fluvial paleochannel systems, red-bed sandstone units, and organic-rich horizons.
Phase 1 Drilling Results
The company completed three drill holes for 939.5m within the Etayo Investigation Permit. Two holes, ET-01 (260.1m) and ET-01bis (296.3m), were drilled from the same pad at the historic Mina Emilia copper mine. ET-01, angled at -45 degrees, intersected interbedded sandstones and lutites with minor copper mineralisation (chalcocite) adjacent to the southernmost adit, returning 0.55m at 0.84% Cu and 11g/t Ag from 75.05m, including 0.25m at 1.39% Cu and 18g/t Ag.
ET-01bis, angled at -60 degrees beneath ET-01, intersected the same lithologies but did not encounter significant copper mineralisation. The absence of organic matter in ET-01bis explains the lack of mineralisation, as organic material provides the reducing conditions necessary for copper precipitation in this deposit type. A third hole, ET-04, located 5.6 km east of Mina Emilia, was completed at 383.1m but encountered no organic matter or copper mineralisation.
Geophysical Survey Findings
A combined downhole and surface Induced Polarisation (IP) test survey on hole ET-04 identified coherent chargeability anomalies at multiple dipoles. The survey revealed possible zones of interest with chargeability values exceeding 30 millivolts per volt at depth. These anomalies recur at the same dipoles for the same transmitting electrode positions, indicating they are considered coherent rather than artifacts. Additional measurements along multiple electrode lines with different orientations are needed to more precisely locate the anomalies.
Phase 2 Drilling Proposal
Megado has notified regional administrative bodies of its intent to undertake Phase 2 drilling within the Etayo and Eslava Investigation Permits, targeting extensions to mineralisation at multiple historical mine workings. The drilling approval process is anticipated to take 1-2 months, with exact scope, timing, and commencement subject to board approval, drill rig availability, permits, and funding. The IBC covers 777.4 sq km across 9 granted permits and 3 application permits, encompassing at least 12 historic copper mines and over 50 documented copper occurrences.