Highlights

  • PDI Gold Limited (ASX:PDI) reported 2026 operating and financial developments across its principal activities.
  • PDI Gold Limited (ASX:PDI) reported indicated mineral resources of 176.0 million tonnes grading 1.22 grams per tonne for 6.9 million ounces of gold as at 30 June 2026.
  • During the June 2026 quarter, PDI Gold Limited (ASX:PDI) reported gold sales of 48,924 ounces and gold poured of 54,252 ounces at Kiniéro and 9,774 ounces at Nampala.
  • Management plans and operating conditions remain relevant to PDI future results.

PDI Gold Limited (ASX:PDI) is a West African gold producer and developer with operations in Guinea and Mali and a development portfolio centred on the Bankan Gold Project. Its 2026 updates cover operating production, mineral resource and ore reserve estimates, and engineering work. The timing of permits remains material to the company’s ability to advance planned development.

Resources and reserves at June 2026

PDI Gold Limited (ASX:PDI) reported indicated mineral resources of 176.0 million tonnes grading 1.22 grams per tonne for 6.9 million ounces of gold as at 30 June 2026. Inferred resources were 87.8 million tonnes at 1.14 grams per tonne for 3.2 million ounces. Combined resources totalled 10.1 million ounces and were inclusive of reserves. Probable ore reserves were 110.9 million tonnes grading 1.34 grams per tonne for 4.8 million ounces. Resources and reserves are different classifications and should not be added together.

The figures should be read in the context of their reporting periods. A quarterly operating outcome cannot automatically be extended across a full financial year, and management guidance can change as conditions develop. Comparing like-for-like periods is important when evaluating whether an apparent change reflects operational activity, timing or a different accounting basis.

Production and operating costs

During the June 2026 quarter, PDI Gold Limited (ASX:PDI) reported gold sales of 48,924 ounces and gold poured of 54,252 ounces at Kiniéro and 9,774 ounces at Nampala. The supplied quarterly summary stated an All-In Sustaining Cost of US$1,408 per ounce and closing cash of A$280.7 million. Production, gold sales and cash balances measure different activities. Costs can vary with sustaining expenditure, processing performance and the timing of mine development.

Operating performance and cash generation are related but not identical. Working capital, capital expenditure, financing activity and the timing of customer receipts or product deliveries can change reported cash balances even when underlying operating activity is relatively stable. This distinction matters when a company is simultaneously operating existing Assets and investing in additional capacity.

Bankan engineering and approvals

PDI Gold Limited (ASX:PDI) reported completion of front-end engineering design for the Bankan process plant and commencement of detailed design. The company has stated that the project cannot proceed under its current development plan without an exploitation permit. Applications relating to Mansounia also remain relevant to access to certain Mining areas. Engineering progress does not remove permitting requirements, and planned production levels are not operating results. Regulatory decisions, construction funding and execution remain significant uncertainties.

Key Insights

PDI Gold Limited (ASX:PDI) combines operating mines with a substantial development programme. Its 2026 resource update provides a basis for understanding the portfolio, but the conversion of development plans into production depends on permits, financing and construction. Operating costs and gold prices also influence the cash available to fund future activity.