Key Highlights

  • Native Mineral Resources (ASX:NMR) reported November doré output of 3,326.1 ounces.
  • Confirmed refined gold for November reached 1,163.5 ounces, with five bars awaiting final results.
  • Approximately 95% of planned maintenance work was completed during a three-day shutdown.
  • Mining and site establishment activities continued across the Charters Towers project.

Native Mineral Resources (ASX:NMR) operates the Charters Towers Gold Project in Queensland, where its Blackjack processing plant produces gold doré from Mining operations. Its shares traded at AUD 0.042 during the 25 November 2026 session, up 5.00%. The company’s latest production update details November output, refinery results and progress on future mill feed.

During the session, the S&P/ASX 200 stood at 8,657.60, down 0.79%.

Blackjack records highest monthly doré output

The 25 November 2026 announcement reported that Blackjack completed its fourth and final smelt for the month on 24 November. Three bars weighing a combined 745.9 ounces, or 23.20 kilograms, were poured. The smelt followed the restart of processing operations after a scheduled maintenance shutdown, with the plant resuming operations on 23 November.

November production reached 3,326.1 ounces of doré across 14 bars, exceeding the previous monthly record of 2,576.6 ounces recorded in August 2026 by 29%. The figures reflect gross doré weight rather than pure gold production. Final refinery results determine the quantities of gold and silver recovered from these bars, making the distinction important when evaluating actual metal output.

Refinery results and November production expectations

The refinery confirmed 285.5 ounces of refined gold and 197.2 ounces of refined silver from two elution bars poured on 17 November. Their official refinery weight was 517.9 ounces, with average assays of 55.12% gold and 38.07% silver. Final results for the two gravity bars from that smelt remained outstanding pending a re-assay.

Confirmed refined gold production for November stood at 1,163.5 ounces when the announcement was issued. Five bars had yet to receive final refinery outturns. Management expects the month's refined gold production to exceed 1,700 ounces, compared with 1,300.2 ounces in October 2026. This remains an expectation rather than a confirmed monthly total.

Maintenance supports processing continuity

The company completed approximately 95% of the planned scope of its three-day maintenance shutdown at Blackjack. The shutdown temporarily reduced production time, but the final November smelt proceeded as scheduled. Completing the work provides an operational basis for continued processing, although future throughput and recovery will remain dependent on plant availability and feed characteristics.

Since production commenced at Blackjack, cumulative confirmed refined metal output has reached 8,356.2 ounces of gold and 8,423.3 ounces of silver. These cumulative measures track actual refinery-confirmed output and are separate from the gross weights of material poured at the processing facility.

Charters Towers mining and future feed sources

Mining continues at the Blackjack Mid Pit and Podosky, while site establishment is underway at Far Fanning. Reverse Circulation Drilling at Blackjack North Pit is expected to conclude in early December 2026. These activities form part of the company's efforts to develop additional sources of material for its processing operations.

Far Fanning and Blackjack North are expected by management to contribute to production plans in 2027. The timing and scale of future contributions will depend on the progress of site development, drilling and operational preparations. The latest announcement did not provide a new quantified annual production forecast for these locations.

Key Insights

November's gross doré output establishes a new operating milestone for Blackjack, but final refined output remains subject to outstanding assay results. Upcoming refinery confirmations will determine whether management’s monthly refined gold expectation is achieved. The progression of additional feed sources and continued processing reliability are separate operational matters that will shape future production updates.