Highlights

  • SQX Resources raised $2,468,000 before costs through a fully underwritten 2-for-3 entitlement offer priced at $0.04 per share.
  • Cash reached $2.4 million at 30 September 2026, up sharply from $583,000 at the start of the quarter.
  • Red Bird drilling returned 45.7 metres at 1.3 grams per tonne gold, with mineralisation open along strike.
  • Williams assays are expected in the December 2026 quarter, followed by electromagnetic surveying and drilling at the Montana project.

In Arizona, shallow gold runs from surface to at least 60 metres depth at Red Bird, and SQX Resources (ASX:SQX) has just refilled its treasury to chase it. A fully underwritten offer lifted quarter-end cash to $2.4 million, and the company has laid out what comes next across Arizona, Montana and Queensland.

Cash rebuilt through an underwritten offer

The 2-for-3 non-renounceable entitlement offer was priced at $0.04 a share and issued 61.7 million new shares. Cash at 30 September 2026 was $2,397,000, against $583,000 at the start of the quarter.

Alpine Capital Pty Ltd underwrote the offer. Directors took up their full entitlements and sub-underwrote up to $130,000 in aggregate. Offer costs came to $105,000, operating outflows were $257,000 and exploration and evaluation spending was $311,000.

Proceeds are earmarked for exploration at Red Bird, Williams and Ollenburgs, assessment of new projects, working capital and offer costs. The company reported no debt or undrawn facilities and estimated 4.21 quarters of funding at current outgoings. Related-party payments totalled $90,000 for director fees, wages and legal services, plus $81,000 for geological and exploration services from director-related entities.

Red Bird: shallow gold, open along strike

SQX holds 80 per cent of Red Bird through its structure. The maiden program comprised 25 reverse circulation holes for 2,509 metres, and results showed gold mineralisation from surface to at least 60 metres depth.

The standout intercepts:

  • RBRC013: 45.7 metres at 1.3 grams per tonne gold from 4.6 metres, including 13.7 metres at 2.2 grams per tonne.
  • RBRC023: 24.4 metres at 3.1 grams per tonne from 22.9 metres, including 9.1 metres at 6.6 grams per tonne.
  • RBRC019: 22.9 metres at 2.8 grams per tonne from 42.7 metres, including 4.6 metres at 8.7 grams per tonne.

The company said mineralisation sits in low-dipping limy conglomerate units across two horizons that converge toward a major north-east striking fault. It remains open along strike, and footwall intercepts west of the mine suggest new prospectivity.

During the quarter SQX advanced an internal resource evaluation and mining scenario work. It also prepared composites from the drilling samples for heap-leach amenability testing, to be sent to a US laboratory. These are exploration results rather than a mineral resource estimate.

Williams and Queensland

The Williams gold-silver project in Montana has eight known vein structures. Field crews mobilised in September 2026 for detailed surface sampling and mapping. The company cited earlier chip-channel samples of 0.6 metres at 75.1 grams per tonne gold and 576 grams per tonne silver, plus a historical stope of 876 tonnes at 141.7 grams per tonne gold. Assay results are expected in the December 2026 quarter, with fixed-loop electromagnetic surveying and drilling to follow.

In Queensland, a technical review of historical data at Ollenburgs and Scrub Paddock is complete. Historical Scrub Paddock results include 28 metres at 1.2 grams per tonne gold from 101 metres. An infill induced polarisation program is planned, and an adjoining application, EPM 28578, awaits a native title agreement.

Gold Butte option and next milestones

SQX also holds an option over the Gold Butte project in Arizona. It costs US$27,250 a quarter for up to eight quarters, or US$225,000 in total, and the company can leave at any time without further obligation. Due diligence continues, and no tenements were acquired or disposed of during the quarter.

The Red Bird and Williams claims are held through AM6 Mining LLC and Stream Metals LLC. Competent person responsibility for the exploration information rests with Dr Julian Stephens, a director of SQX.

For the December 2026 quarter the company listed completion of Red Bird mining scenario work, planning of the next expansion-focused exploration phase, receipt of Williams assays, finalising the Queensland programs, and continued evaluation of further opportunities.