Highlights

  • The Oropesa Tin Project, the only tin project in advanced development within the European Union, has received multiple Spanish government approvals in 2026, with a General Interest Declaration granted in November 2026.
  • Elementos holds a binding, unconditional Call Option to acquire 50% of Iberian Smelting SL and its Robledollano tin smelter, creating a potential vertically integrated mine-to-metal tin Supply chain within the EU.
  • Tin prices have averaged approximately US$49,900 per tonne over the 12 months to November 2026, approximately 66% above the DFS reference price of US$30,000 per tonne used in the April 2025 feasibility study.
  • A 3,600-metre diamond drilling programme commenced at the Cleveland Tin and Tungsten Project in Tasmania in early November 2026, targeting resource extensions across tin-copper, tungsten, and other critical minerals.

Elementos Limited (ASX:ELT) presented its 2026 Annual General Meeting update, highlighting progress toward a final Investment decision for the Oropesa Tin Project in Spain, the value of the smelter option, and an active period for the Cleveland Tin and Tungsten Project in Tasmania. The company holds two advanced tin projects: Oropesa, the only tin project in advanced development within the European Union and one of the few vertically integrated mine-to-metal tin platforms globally, and Cleveland, a historical tin-copper mine in northwest Tasmania with a growing multi-commodity resource base.

Oropesa Regulatory Progress and Government Support

A series of regulatory milestones have been achieved at Oropesa in 2026. In March 2026, tin was named a Priority Raw Material under Spain's National Mining Exploration Program 2025 to 2030. In June 2026, the Regional Government of Andalucia declared Overriding Public Interest for the project, legislating a clear regulatory pathway for EU Water Framework Directive compliance. In July 2026, the Provincial Council of Córdoba formally approved site access and public road upgrades for heavy plant and operational logistics. The most recent milestone was a General Interest Declaration granted in November 2026, which facilitates the reclassification of land from forestry to mining use — a requirement for the project's Unified Environmental Authorisation (AAU).

Three primary permits remain outstanding for a final investment decision: the Unified Environmental Authorisation (AAU), the Exploitation Permit (mining licence), and the finalisation of offtake and debt financing. The company describes 2027 as the year for converting permitting progress into a final investment decision, with these three elements constituting the critical path.

Smelter Option and Mine-to-Metal Strategy

Elementos' call option to acquire 50% of Iberian Smelting SL — the owner and operator of the Robledollano tin smelter in Extremadura, Spain — became binding and unconditional in August 2026. The smelter is located approximately 220 kilometres from the Oropesa mine site, within trucking distance, and is a licensed operating facility. Exercise of the option would create a rare vertically integrated tin supply chain within the European Union, from mine through concentrate processing to refined tin metal — the only primary domestic tin supply in the EU, as Europe and North America currently produce no tin.

European and North American tin buyers are reported to pay a premium above the LME reference price for refined metal from supply chain-secure sources, and Elementos cites this as a commercial advantage of the mine-to-metal model. The initial 12-year life of mine at Oropesa is projected to produce approximately 5,400 tonnes of tin concentrate per year, representing approximately 10% of European tin Demand and approximately 1% of global supply. The DFS Economics were modelled at a reference tin price of US$30,000 per tonne; the current Spot Price of approximately US$48,000 per tonne substantially exceeds this reference.

Cleveland Drilling and Multi-Commodity Potential

A 3,600-metre diamond drilling programme commenced at the Cleveland Tin and Tungsten Project in Tasmania in early November 2026. The programme targets three areas: untested tin-copper extensions between historically productive tin lodes; the Foleys Zone tungsten exploration target, which has an Inferred Mineral Resource of 8.49 million tonnes at 0.24% tungsten trioxide and a conceptual exploration target of 32 to 90 million tonnes; and additional critical minerals intersections targeting molybdenum, bismuth, rubidium, and fluorite. A single drill pad with a parent hole and daughter holes will minimise surface disturbance while providing multiple intersections across the target zones.

Cleveland operated as an underground tin mine for 27 years and has existing JORC Mineral Resources for tin-copper (7.47 million tonnes at 0.75% tin and 0.30% copper), tungsten, and tailings. The 2026 drilling campaign aims to build the case for Cleveland as a multi-commodity system, particularly given the growing strategic interest in tungsten as a critical mineral with applications in hard metals, defence, and energy sectors. Drilling results and study updates are expected to follow the current programme.

Key Insights

The sequence of government approvals received in 2026 — Priority Raw Material designation, Overriding Public Interest, infrastructure approvals, and the General Interest Declaration — constitutes a material de-risking of the Oropesa permitting pathway, with the AAU and Exploitation Permit as the remaining major regulatory milestones.

The binding smelter option differentiates Elementos from pure-play tin mine developers by providing access to the full value chain, with the premium that EU and North American buyers pay for supply-chain-secure refined tin representing a potential source of above-DFS economics.

At current tin prices approximately 61% above the DFS reference price, the project economics under the DFS sensitivity analysis would substantially exceed the base case, though no revised economic assessment has been published to reflect current prices.