Highlights

• Cyprium Metals said the Phase 1 Copper Cathode Restart at Nifty has advanced materially toward practical completion.

• The new acid terminal has been commissioned, with sulphuric acid deliveries recommencing for the first time since the SXEW plant closed in 2006.

• Operational readiness and pre-commissioning activities are underway across key parts of the project.

• Heap leach systems have commenced hydro-testing across surface leach and injection leach programs.

• SX area tanks have been recertified, while electrowinning cells have been delivered, cleaned and installed.

Cyprium Metals Limited (ASX:CYM) has provided a detailed operations update on the Nifty Copper Complex in Western Australia, with the company reporting progress across the Phase 1 Copper Cathode Restart program. The update shows work advancing across several major project areas, including acid storage, heap leach systems, ponds, solution handling, solvent extraction, electrowinning, firewater infrastructure and electrical systems.

Cyprium Metals shares closed at AUD 0.38 on 25 June 2026, down 7.32% for the session. Despite the decline on the day, the stock remains up 46.15% over the past year.

About Cyprium Metals

Cyprium Metals is an Australian copper company focused on redeveloping the Nifty Copper Complex in the Paterson region of Western Australia. Nifty has previously produced copper from both oxide and sulphide resources and remains the company’s flagship asset.

The project benefits from existing infrastructure, a long operating history, established data, operational approvals and recent investment. Cyprium is pursuing a staged restart strategy, with the first phase focused on copper cathode production through the heap leach, solvent extraction and electrowinning process.

Beyond Nifty, the company holds additional copper-focused assets across the Paterson and Murchison Provinces, including projects with defined resources and exploration targets. Cyprium’s stated focus is to become a near-term copper producer through a phased restart at Nifty while maintaining a longer-term copper growth pipeline.

Nifty Restart Moves Toward Completion

The latest update indicates that Cyprium’s Phase 1 Copper Cathode Restart has moved into a more advanced stage.

The company said the June quarter to date has involved intensive execution across major work packages. These included acid storage, ponds, heap leach infrastructure, solvent extraction, electrowinning, solution handling, filtration, firewater and electrical systems.

As more work packages near completion, Cyprium said its focus is shifting from construction and refurbishment toward practical completion, commissioning and operational readiness.

Executive Chairman Matt Fifield said the receipt of sulphuric acid on site is a clear marker of where the project now stands, with activity moving from building toward completion and commissioning.

Acid Supply Resumes After Around 20 Years

One of the key milestones in the update is the commissioning of the new acid storage and distribution terminal.

Following regulatory sign-off, sulphuric acid deliveries to Nifty recommenced in late May. Cyprium said this was the first acid delivered to the site since the solvent extraction and electrowinning plant closed in 2006.

The company has arrangements in place to procure acid through one of Australia’s major sulphuric acid handlers. Acid is delivered by sea to the supplier’s terminal in Port Hedland, which currently holds up to five months of Cyprium’s forecast acid requirements.

From Port Hedland, specialised tanker trucks transport the acid to the Nifty site, where it is discharged into the new acid terminal.

The recommencement of acid deliveries is important for the planned leaching operations, as sulphuric acid is required for copper recovery from oxide material through the heap leach process.

Heap Leach Systems Enter Testing Phase

Cyprium also reported progress across the heap leach pads and leaching infrastructure.

Preparation for the initial surface leach program has continued, including turnover of surface materials on selected heaps, installation of on-flow piping and dripper hose, and testing and pressurisation of solution systems.

The turnover pads are expected to be flushed with water and then commissioned with acid in coming weeks, subject to regulatory sign-off on heap leach ponds and drainage work.

In parallel, Cyprium has started a trial of direct injection leaching. This method is being tested as a way to increase the volume of material under leach by applying solution through vertical injection.

The trial includes drilling and casing shallow wells into the heaps, injecting acid solution and establishing the required solution piping and pump support. Cyprium said initial indications have been promising, with the wellfield flushed with water, and the trial remains ongoing.

Ponds and Solution Infrastructure Advance

Pond and solution infrastructure readiness has also advanced materially.

Cyprium said commissioning of pond and solution infrastructure is expected in coming weeks, subject to regulatory sign-off. Recent work has focused on installing new pumps and piping to support leaching infrastructure, along with remedial work on pond linings for compliance.

Key tasks included installation and suction pipework for the ILS1 pump, commencement of ILS1 pond filling after normal operating envelope sign-off and progress toward full energisation of ILS1 by quarter-end.

The company also reported continued installation of PLS1 pump and associated pipework, completion of raffinate pond readiness, installation of cable trays and control circuits across ILS and PLS areas, field device installation, internal motor control centre wiring and confirmation of stormwater discharge system adequacy.

Solvent Extraction Plant Nears Commissioning Preparation

The solvent extraction plant has also seen substantial progress.

Cyprium said structural repairs and acid proofing in the solvent extraction plant have been completed and received regulatory sign-off. Current activity in the area is increasingly focused on commissioning preparation rather than construction.

During the quarter, all SX area tanks were cleaned and inspected. The SX bund and sump passed hydrotesting requirements, while pipework was reinstated across primary settlers, mixing tanks, raffinate systems, crud and clay circuits, loaded surge tank, reagent tanks and guar gum tank.

The company also removed redundant pipework and cabling. Two primary mixer motors were delivered and installed, while agitators were repaired off-site and are being returned to site for installation. Fibreglass repair, concrete repair and acid coating works have also been completed.

Electrowinning Plant Progresses Across Key Areas

Cyprium reported substantial progress in the electrowinning area during the quarter.

Work included completion of concrete repairs around the circulation tank and sump, application of acid-proofing to the circulation tank bund and cell area, installation of HDPE pipework and supports, and completion of lining repairs and hydrotesting.

The electrowinning compressor was delivered and installed, while cell inserts were delivered, cleaned and progressively installed. Busbar upgrade and reinstallation were completed, the transformer was delivered and work on the rectifier pad advanced.

The overhead crane has been fully installed, and the stripping machine has been cleaned, inspected and partly refurbished. Delivery of anodes has also commenced, while high-voltage testing continues.

Anodes and cathodes, which are used to plate copper in the electrowinning plant, have started arriving on site.

Electrical Reinstatement Continues

Electrical and instrumentation work remains a major focus before commissioning.

Cyprium said restoring power, control and monitoring systems across the full SXEW circuit is essential for the restart. The company has been working through cable removal, installation, testing and termination across motor control centre and field areas.

Work completed or advanced during the quarter included removal of redundant cables across SXEW and MCC areas, testing and sign-off of existing MCC power cables, circuit breaker testing, installation of cable trays to raffinate pumps and settlers, installation of sump pump infrastructure and completion of ILS1 pump rewiring.

The company also commenced a programmable logic controller study for the electrowinning plant.

Operational Readiness Work Underway

Cyprium said the quarter marked a transition toward pre-commissioning and commissioning preparation.

Operational readiness activities included preparation of manuals and procedures, training system upgrades, laboratory fitout, mine rescue preparation, acquisition of safety and hazardous materials equipment, initial deliveries of first-fill materials, warehouse stocktake and enterprise resource planning protocols.

These steps are intended to support the shift from refurbishment into production readiness.

Growth Work Also Progressing

In addition to the Phase 1 restart, Cyprium is advancing technical and commercial work for future growth initiatives.

The company said the expansion of SXEW cathode production capacity is likely to be the first major growth step beyond the current restart. Planning work and capital estimates are underway for further refurbishment that could lift targeted cathode production capacity from around 6,000 tonnes per annum under Phase 1 to around 20,000 tonnes per annum.

Cyprium noted that increased plant capacity would depend on generating more copper in leach. This could be achieved by increasing the mining rate of existing heap leach pads and/or using additional oxide material from surface stockpiles and the open pit.

Open Pit Oxides and Sulphides Under Review

Cyprium continues to evaluate shallow oxide material in the Nifty open pit.

The company said the 2024 Nifty pre-feasibility study did not include shallow oxide material in the cathode operations because further assessment was needed. That material was assumed to be stockpiled as waste during mining to reach sulphide ores.

Cyprium has now advanced evaluation of the shallow oxide material through additional drilling and mine planning. It expects to report updated Mineral Resource and Ore Reserve estimates for the Nifty Copper Complex during the second half of CY2026.

The company is also refining plans for open pit mining and the refurbishment of the existing Nifty concentrator, including expected capital costs, mine engineering, scheduling and operating costs.

What This Means for Investors

Cyprium’s latest update shows continued progress toward restarting copper cathode production at Nifty. The recommencement of sulphuric acid deliveries, advancement of heap leach testing, SX and EW plant readiness, pond infrastructure work and operational preparation all point to a project moving closer to commissioning.

The key investor focus from here is likely to be the practical completion of remaining work packages, regulatory sign-offs, commissioning progress and the company’s updates on growth initiatives in the September quarter. Longer-term, investors will also watch the planned Mineral Resource and Ore Reserve updates expected during the second half of CY2026, as well as the potential pathway to expand SXEW capacity beyond Phase 1.