Key Highlights

  • Chalice Mining (ASX:CHN) commenced a three-stage processing pilot for the Gonneville project in November 2026.
  • The programme uses about five tonnes of fresh sulphide ore drawn from ten diamond drill holes.
  • The company is targeting a definitive feasibility study in the second half of 2027.
  • Environmental assessment, project finance and metallurgical results remain prerequisites for a development decision.

Chalice Mining (ASX:CHN) is developing the Gonneville palladium, nickel and copper project in Western Australia while pursuing exploration opportunities elsewhere. In November, the company began a pilot programme intended to test its proposed processing sequence. The pilot, approvals work and financing strategy will inform whether its development schedule can progress toward later feasibility and Investment decisions.

Pilot plant tests the proposed processing sequence

On 11 November, Chalice said it had started a pilot programme to test the full processing flowsheet for Gonneville, its palladium, nickel and copper project north-east of Perth. Ten diamond holes supplied about five tonnes of fresh sulphide ore, chosen to represent early plant feed. The programme runs in three stages. A one-week flotation pilot comes first, followed by two leach pilots. The first, on flotation tails, starts in late November, and the second, on a blend of oxide ore and sulphide tails, starts in January. The pilot is designed to produce a copper-PGM-gold concentrate, a nickel-cobalt-PGM concentrate and a PGM doré. An independent technical engineer is overseeing the work on behalf of prospective lenders. Chalice also reported a simpler leach process than assumed in its pre-feasibility study (PFS). The number of elution steps has been cut from five to two, and a nickel-based stripping solution has replaced a zinc-based one.

Gonneville scale and feasibility timetable

Chalice has presented Gonneville as a plan for Australia's first primary PGM mine. The company’s AGM material described that the PFS released in December 2025 outlined a maiden ore reserve of 260 million tonnes containing 7.1 million ounces of palladium, platinum and gold (3E). It also gave a pre-tax net present value of A$1.4 billion and pre-production Capital costs of A$820 million. Chalice plans to fund 60–70% of that capital with senior debt, mainly from export Credit agencies. A definitive feasibility study is due in the second half of 2027, with a final investment decision targeted for the first half of 2028. The company has pointed to first production in 2030.

Kestrel exploration and September-quarter liquidity

The 2 November discovery, called Kestrel, sits about 65km west-north-west of Tennant Creek on ground Chalice owns outright. The first hole returned 27m at 0.42% copper and 4.83g/t gold, including 15m at 8.56g/t gold. Mineralisation has been tested over about 500m of strike, and assays for eight more holes were pending. Chalice reported about $53 million in cash and listed investments at 30 September. Exploration and evaluation payments were about $6.7 million in the quarter.

Environmental review and financing challenges

Chalice has said environmental approvals are the critical path to a final investment decision. In its September Quarterly Report it said it expected to submit its environmental review documents to state and federal regulators in the December quarter of 2026. The WA EPA has set a Public Environmental Review level of assessment, the federal government has declared it a controlled action, and approvals timing remains a key uncertainty. Funding is the other major hurdle. A development of this size will need substantial Debt and equity, as well as offtake agreements that are not yet in place. Returns are also sensitive to palladium and nickel prices, which can be volatile. Early-stage drilling results, such as those at Kestrel, may not lead to an economic deposit.

Key Insights

The disclosed milestones remain conditional on further operating, technical or commercial steps. The company-specific evidence provides a basis for monitoring progress without assuming outcomes.