Highlights
- Tritton copper production ran ahead of plan in the September quarter, with record September monthly mill throughput of 166,000 tonnes.
- The Golden Plateau Mineral Resource at Cracow increased by 140,000 ounces after quarter-end, reaching 3.0 million tonnes at 2.1 grams per tonne for 200,000 ounces.
- Constellation copper waste stripping started in August 2026, with site infrastructure on schedule and first ore to the mill targeted for March 2027.
- Closing cash was A$127.8 million with no debt, and both Tritton and Cracow are on track for FY27 annual guidance.
Three operations running to plan, one resource growing sharply and a fourth project moving earth toward first production — Aeris Resources (ASX:AIS) delivered a September quarter that combined operational steadiness with concrete progress at Constellation, its copper development in South Australia. A 140,000 ounce step-up in the Golden Plateau gold resource at Cracow after the period closed added a further layer to an already positive update, bringing that deposit to 200,000 ounces and signalling continued exploration upside at an existing mining centre.
Tritton Running Ahead of Plan
At Tritton in New South Wales, ore milled was 452,000 tonnes for the quarter. Milled grade eased to 1.47% copper from 1.61% and recovery to 88.4% from higher levels, but September set a record monthly mill throughput of 166,000 tonnes. Aeris attributes the strong throughput to better-than-planned mined grades from the Murrawombie open pit, which is due to finish in November 2026. Higher-grade Budgerygar ore is supporting underground output as the open pit winds down. Drilling at Avoca Tank identified approximately 120,000 tonnes of additional ore, being prepared for mining in late FY27.
Cracow in Queensland produced 8,800 ounces of gold from 157,300 tonnes milled at 1.97 grams per tonne for the quarter. Lower-grade stope sequencing affected the result, and the company expects milled grade to improve in the December quarter as higher-grade material is accessed. Group quarterly output was 5,900 tonnes of copper, 10,800 ounces of gold and 48,800 ounces of silver. The company says both Tritton and Cracow are on track for FY27 annual guidance of 22–27 kilotonnes copper, 42–51 kiloounces gold and 130–160 kiloounces silver.
Golden Plateau Resource Grows to 200,000 Ounces
After quarter-end, on 22 October 2026, Aeris released an updated Golden Plateau Mineral Resource of 3.0 million tonnes at 2.1 grams per tonne gold, containing 200,000 ounces of gold and 750,000 ounces of silver — an increase of 140,000 ounces on the previous estimate released on 30 July 2026. About half of the contained gold is classified in the Measured and Indicated categories.
This is a resource estimate, not a reserve or development decision. The company plans 15,000 metres of drilling at Golden Plateau in FY27, alongside continued mine design and metallurgical work, and is targeting permitting for FY28 development.
Constellation Copper Project Taking Shape
Constellation waste stripping started in August 2026, marking a visible transition from studies to active construction. About 5 kilometres of a 25-kilometre haul road has been sealed, the project water pipeline is complete and site infrastructure is on schedule. First ore to the mill is targeted for March 2027.
Growth and project spending rose to A$53.6 million from A$23.5 million in Q4 FY26, mostly directed at Constellation development. FY27 guidance for growth capital is A$170–210 million, and Aeris says full-year spend remains on track within that range. All-in sustaining cost was A$6.10 per pound of copper equivalent, against A$4.83 in Q4, reflecting lower grade throughput and higher sustaining capital of A$25.4 million.
Balance Sheet and Other Items
Closing cash was A$127.8 million with no debt. Usable cash plus Tritton receivables was A$178.7 million, down from A$202.3 million at 30 June, reflecting Constellation development spending. The balance sheet positions Aeris to fund the project build without near-term financing pressure.
At Jaguar in Western Australia, scout drilling across eight holes returned no significant intersections from completed assays, and the company will conduct follow-up gravity and electromagnetic modelling in the December quarter before determining further drilling targets. The Stockman feasibility study in Victoria has been delayed by mine plan improvements and metallurgical work, with release now expected in the second half of FY27.