Key Highlights

  • Dalrymple Bay Infrastructure Limited (ASX:DBI) has released a 28-page investor presentation prepared for a site visit to the Dalrymple Bay Terminal (DBT) at the Port of Hay Point in Queensland on 25 November 2026.
  • The terminal's 84.2Mtpa capacity is fully contracted on a 100% take-or-pay basis to June 2028, with evergreen renewal options.
  • The company has 10 customers across 21 mines, and 84% of its Revenue comes from mines that are predominantly metallurgical coal.
  • DBI said adding SL1A, RL4 and other NECAP programs to the asset base on 1 July 2027 would increase the NECAP charge by about $0.53/t, and that every additional $0.10/t of TIC equals about $8.5m of revenue a year.

Dalrymple Bay Infrastructure Limited (ASX:DBI) has released a 28-page investor presentation prepared for a site visit to the Dalrymple Bay Terminal (DBT) at the Port of Hay Point in Queensland on 25 November 2026.

The presentation sets out how the terminal works, how its charges are structured and where future growth in its asset base could come from. For investors who follow the infrastructure owner, it brings together contract terms, recent capital projects and the 8X expansion option in a single document.

What did Dalrymple Bay Infrastructure announce?

DBI described DBT as the largest metallurgical coal export Facility globally, citing a 14% share of 2025 global seaborne metallurgical coal exports based on AME data.

The terminal's 84.2Mtpa capacity is fully contracted on a 100% take-or-pay basis to June 2028, with evergreen renewal options. DBI said it collects a Terminal Infrastructure Charge (TIC) of $4.02/t on every contracted tonne, and that terminal operating and maintenance costs are passed through to customers in full. The company has 10 customers across 21 mines, and 84% of its revenue comes from mines that are predominantly metallurgical coal. The current pricing arrangement expires in 2031.

The presentation also covered non-expansion Capital Expenditure (NECAP):

$97.8m ($91.3m plus $6.5m of interest during construction) was added to the asset base on 1 July 2026, lifting the TIC by $0.15/t.

The Shiploader 1 replacement (SL1A), with a budget of $165.4m excluding interest during construction, was completed on 14 November 2026, on time and on budget.

The Stacker Reclaimer 2 replacement (RL4), budgeted at $115.6m, was due for construction completion by the end of November 2026, with handover expected in January 2027.

Phase 1 of an offshore gallery wrapping program ($33m) began in September 2026. The full program has indicative capex of about $150m over six years.

DBI said adding SL1A, RL4 and other NECAP programs to the asset base on 1 July 2027 would increase the NECAP charge by about $0.53/t, and that every additional $0.10/t of TIC equals about $8.5m of revenue a year. These outlook figures were labelled indicative and rest on stated assumptions, including about $300m of direct capex and a 10-year bond rate of 4.5%.

On the 8X expansion, DBI outlined a path to 99.1Mtpa of contracted capacity across three phases, totalling 14.9Mtpa at an estimated cost of $1,583m. It said all primary environmental approvals were secured, about 35Mtpa of annualised Demand sits in the access queue, and financing Options are being explored.

Related Sector Context

Industrial businesses serve customers through manufacturing, equipment, infrastructure and specialist services. Contract timing, utilisation, procurement costs and Working Capital requirements influence operating performance and Investment decisions.

Risks to Watch Out

The 8X expansion remains an option rather than a commitment. DBI said it retains flexibility on how many phases to pursue, subject to commercial negotiations, customer commitments and a final investment decision.

Changes in input costs, customer demand and operating efficiency may affect profitability. Investment and working capital requirements can reduce cash available for other priorities. The timing of customer orders and the ability to deliver services or products at expected costs remain important considerations.

Project delays, changes in customer demand and higher input costs could affect margins and cash conversion. Capital expenditure and working capital requirements may compete with other financial priorities. Planned operating improvements depend on implementation and customer uptake.

What should investors watch next?

Investors may be watching for confirmation of the RL4 handover, expected in January 2027, and for the NECAP additions scheduled for 1 July 2027.

Any progress on 8X customer commitments, financing or a final investment decision would also be relevant. Contract renewal options, which must be exercised at least 12 months before expiry under the June 2028 contracts, may also draw attention.