Highlights
- Dry commissioning is underway at Edna May, with first gold targeted for December 2026.
- A long-term sodium cyanide Supply agreement has been executed.
- About 60,000 tonnes of ore sits on the Edna May run-of-mine pad.
- Lake Johnston holds more than 180,000 tonnes of ore.
- Plant capacity, reserves and costs were not disclosed.
Forrestania Resources Limited (ASX:FRS) operates a two-hub gold strategy in Western Australia, with Edna May and Lake Johnston as its processing centres. On 20 November 2026 the company set out operational steps it says position Edna May for first gold, targeted for December 2026. Dry commissioning is well underway and the next stage is wet commissioning.
Contracts and People
Forrestania (ASX:FRS) has executed a long-term sodium cyanide supply agreement with Australian Gold Reagents Pty Ltd for Edna May. Cyanide is the reagent used to dissolve gold from crushed ore in conventional leach circuits, so securing supply is a precondition for wet commissioning and steady processing. The value and duration of the agreement were not disclosed.
Campbell Gold Haulage Pty Ltd has been awarded the ore loading and crusher feed contract covering both Edna May and Lake Johnston. Campbells already holds the company's road train contract, and its equipment and personnel are mobilising. MEGA Resources remains the principal Mining contractor, and the two businesses share a new Kalgoorlie office that the company describes as its Goldfields operations hub. Darren Gaby has been appointed General Manager Mining, bringing more than three decades of Goldfields experience.
Ore on Hand at Two Hubs
About 60,000 tonnes of ore is reported to be sitting on the run-of-mine pad at Edna May. Lake Johnston holds more than 180,000 tonnes, with its stockpile described as close to full capacity and inventories still building.
Third-party material forms part of the feed plan. Forrestania (ASX:FRS) has an ore purchase agreement with Star Minerals covering the Tumblegum deposit, although its terms were not given. In mid-November it also signed a binding ore purchase agreement with Western Gold Resources, which is advancing the Gold Duke project near Wiluna, and agreed to become that company's cornerstone shareholder.
Management Commentary
Executive Chairman David Geraghty said first ore processing at Edna May is fast approaching and described the latest initiatives as important milestones in the systematic build-out of the company's operating platform. He added that the focus is on ensuring every element of each operation is in place for a successful transition to production.
These are management statements about readiness rather than evidence of output. Until wet commissioning is complete and ore is running through the circuit, throughput, recoveries and the timing of the first pour remain targets. The company has framed the work as part of its evolution from developer to producer.
What Remains Undisclosed
Plant capacity, ore reserve figures, forecast production, costs and funding headroom were not stated, and no contract values were disclosed. Stockpile tonnages were given without grades, so the gold content of the ore on hand cannot be assessed from this update.
The disclosed next step for Forrestania (ASX:FRS) is the move from dry to wet commissioning at Edna May, followed by first ore processing and a targeted December pour.
Key Insights
Forrestania (ASX:FRS) has put reagent, haulage and mining arrangements in place and holds ore at two hubs as it prepares for wet commissioning. First gold remains a December target, and key operating and financial details have not been disclosed.