Highlights
- BlueScope (ASX:BSL) reported FY26 underlying EBIT of A$1.27 billion and net profit after tax of A$802 million.
- North America generated about A$1 billion of underlying earnings.
- The New Zealand electric arc furnace is ramping up, while the New Zealand and Pacific segment posted an underlying EBIT loss of A$21.8 million.
- BlueScope plans A$3.00 per share in returns for each of calendar 2026 and 2027.
- First-half FY27 underlying EBIT is guided at A$860 million to A$960 million.
BlueScope Steel Limited (ASX:BSL) announced its FY2026 result on 17 August, the first full year under managing director Tania Archibald. The company describes the year as the point where it moved from a heavy Investment phase to delivery. A central piece of that investment is the electric arc furnace at New Zealand Steel's Glenbrook site, which replaces coal-based steelmaking with scrap-based production.
FY26 Earnings
Underlying EBIT was A$1.27 billion, up about 72%, and net profit after tax was A$802 million, which is not a like-for-like comparison because an Impairment charge in FY25 did not repeat. North America was the standout, with underlying Earnings of about A$1 billion, led by the North Star electric arc furnace mill in Ohio. South-East Asia delivered a record result, and Australia recorded record COLORBOND and TRUECORE sales. BlueScope (ASX:BSL) completed a A$200 million cost program and expects a further A$150 million of benefits in FY27.
The Glenbrook Electric Arc Furnace
The new electric arc furnace at New Zealand Steel is being ramped up and is intended to cut coal use and lower emissions by melting scrap steel with electricity. The New Zealand and Pacific Islands segment recorded an underlying EBIT loss of A$21.8 million, compared with a profit of A$1.9 million, reflecting difficult market conditions during the transition. BlueScope (ASX:BSL) said product quality improvements from the new furnace are on track for delivery in the middle of next calendar year.
Australian Steelmaking and Capital Projects
In Australia, BlueScope continues to assess lower-emissions technologies. The No. 6 Blast Furnace reline has been pushed back to early in the 2027 financial year because of the scale and complexity of the project and cost inflation. A new metal coating line in Western Sydney and a plate mill upgrade are moving into ramp-up. BlueScope (ASX:BSL) says the plate mill adds heavy plate capability for defence, infrastructure and renewables.
Returns and Outlook
The company plans total distributions of A$3.00 per share in calendar 2026 and again in calendar 2027, including special dividends. A Special Dividend of A$1.00 was paid in February 2026, and a further 70 cent unfranked special dividend was declared with the result. First-half FY27 underlying EBIT is expected to be A$860 million to A$960 million, supported by North American strength, solid Australian Demand and an early recovery in New Zealand. BlueScope (ASX:BSL) remains exposed to steel spreads and trade policy.
Key Insights
BlueScope (ASX:BSL) shifted from investment to returns in FY26, with strong North American earnings offsetting New Zealand losses while its electric arc furnace ramps up. The furnace's performance, the Port Kembla decision path and the first-half FY27 earnings range are the main items to follow.
_11_26_2026_09_15_23_079993.jpg)