Key Highlights

  • Tlou Energy (ASX:TOU) continued to generate electricity for the Kala Data Centre at proof-of-concept scale during the September 2026 quarter.
  • Recurring coal fines and pump inefficiencies led the company to temporarily shut the Lesedi 6 well.
  • The Lesedi substation was about 90% complete, with remaining work deferred while Tlou seeks funding.
  • Tlou had drawn AUD 7.13 million of its AUD 10 million Shareholder Loan Facility by quarter-end.

Tlou Energy (ASX:TOU) is developing an integrated gas-to-power project at Lesedi in Botswana. During the September 2026 quarter, it continued supplying the Kala Data Centre at proof-of-concept scale and assessing what a larger facility would require. Production testing at Lesedi encountered recurring coal fines, and Tlou temporarily shut one well while continuing to collect data from another.

How Lesedi Supplied Kala During the Quarter

Lesedi combines coal bed methane wells, gas gathering infrastructure and on-site generation. Tlou used electricity from the project to continue operating Kala at proof-of-concept scale. Its expansion planning covered possible improvements to the existing gas-to-power process as well as the additional Supply and infrastructure a larger facility would need.

Tlou continued testing and dewatering at Lesedi 4 and Lesedi 6 during the quarter. Recurring coal fines affected operations and, together with pump inefficiencies, prompted a temporary shutdown of Lesedi 6. At Lesedi 4, monitoring and data collection continued to assess how the well was performing and what it could contribute to gas supply for any planned expansion.

Sector Context for Gas, Solar and Grid Power

Tlou's development work spans gas-fired generation, potential solar generation and a grid connection. The company is evaluating whether solar could support future Kala operations and supplement supply when less gas is available. It is considering an initial solar development of 5 megawatts, with possible expansion and storage also under review. The solar proposal is subject to funding, approvals and further assessments, and Tlou reported no binding agreement.

The Lesedi substation is intended to connect generation at the site to the grid for electricity sales and to accommodate gas and solar generation. The company estimated that construction was approximately 90% complete. Remaining work was deferred until funding became available, with grid connection still identified as a development priority.

Risks to Watch in Well Performance and Funding

Expansion depends on sustainable gas flow, reliable electricity generation, funding and approvals. Tlou said further development planning would consider power and infrastructure Options without assuming an increase in available gas. The company is also evaluating on-site plant reliability and maintenance schedules as part of its effort to sustain operations.

Unaudited cash stood at approximately AUD 57,000 on 30 September. The Quarterly Report recorded AUD 201,000 in net operating cash outflow, AUD 237,000 in investing outflow and AUD 370,000 in financing inflow. Tlou reported approximately AUD 2.93 million in total available funding at the end of September, comprising both quarter-end cash and available financing. Tlou had approximately AUD 2.87 million undrawn under its shareholder loan. It described the facility as a bridge to support ongoing operating costs while it pursues further capital, and said material development work requires additional funding.

What Lies Ahead for Kala and Lesedi

Tlou plans to continue testing Lesedi 4 and assess what power and infrastructure could support a larger Kala operation. The company also identified electrical network mapping, engagement with authorities and discussions with potential funding partners among its upcoming work. It has yet to give a date for a commercial-scale expansion in the quarterly report.

Kala operated during the quarter using electricity generated at Lesedi. Plans to increase its scale, complete the grid connection or add solar remain at different stages. Their progress depends on the results of technical work and the availability of additional capital.