Vintage Energy Ltd (ASX:VEN) is an Australian oil and gas company with interests in Southern Flank gas fields in the Cooper Basin, including the Odin and Vali fields, and an interest in the Cullen-1 well in the Northern Territory. On 30 July 2026 it released its Quarterly Report for the period ended 30 June 2026.
Production and sales
Sales Revenue for the quarter was $0.58 million, down 20% from $0.74 million in the prior quarter, which the company attributes chiefly to lower gas production. Production was 0.05 petajoule equivalent (PJe), down 17%, with sales gas accounting for 90% of production. For FY26, sales revenue was about $3.0 million, down 35% from about $4.66 million, and production was 0.24 PJe, down 38%.
South Australian grants
Grant agreements with the Government of South Australia were executed for two grants of $2.5 million each to the PRL 211 and ATP 2021 joint ventures, in which Vintage holds 50%. The grants provide cornerstone funding for drilling the Odin-3 and Vali-4 gas production wells, and the company expects them to fund up to 50% of the drilling cost. Vintage is planning to drill the wells in the 2027 financial year, subject to joint venture approvals and rig availability. The total $5 million was received on 24 June 2026 and is recognised as restricted cash because it is reserved for the drilling.
Entitlement offer and cash position
A 1-for-4 non-renounceable entitlement offer at 0.4 cents per share closed on 17 April 2026 and raised approximately $1.35 million before costs through the issue of 337,135,604 shares, each with two free attaching unquoted Options exercisable at 0.5 cents and expiring on 24 April 2028. A shortfall offer, which closed on 17 July, raised a further $65,146.
Total cash and cash equivalents were $3.97 million, including restricted cash of $2.63 million. Unrestricted cash was $1.34 million, compared with $0.58 million at 31 March 2026. Net cash from Operating Activities was an inflow of $2.26 million, largely reflecting the grant receipt. Borrowings, net of unrestricted cash, were $8.66 million, compared with $9.42 million at the start of the quarter.
Cullen-1 Heads of Agreement
On 21 April 2026 the company announced a Heads of Agreement with Vault Energy for the Supply of gas that could be produced from Cullen-1 in the Northern Territory, if testing is successful. The agreement commits Vintage and Vault to work exclusively together on a gas sales agreement. Vault Energy is described as an Australian energy company using advanced technologies to convert surplus energy into computing resources, and the company says extended test flows from Cullen-1 could provide Volume for modular data centre technology located near the well. An environment management plan application for testing activities is being prepared.
Risks and sector context
Revenue and production fell over the quarter and the year. The grant funds are restricted to drilling the two wells, and the drilling timing depends on joint venture approvals and rig availability. Borrowings net of unrestricted cash remain $8.66 million. The Cullen-1 agreement is a Heads of Agreement that depends on successful testing and a gas sales agreement, and testing has not begun. The entitlement offer was only partly taken up, with 184,592,387 shares left as shortfall at the close of the offer.
For sector context, the Odin and Vali fields are in the Cooper Basin and supply gas under contracts, and the company refers to uncontracted Cooper Basin gas reserves.
What to watch next
Items to watch include joint venture approval and rig availability for Odin-3 and Vali-4 in FY27, production from the fields, progress on the environment management plan and testing at Cullen-1, any gas sales agreement with Vault Energy, and funding and commercial agreements the company says it is seeking.