Highlights
- A five-year Landau-Ost licence has been secured in Rhineland-Palatinate.
- The licence adjoins the Lionheart project, which is under construction.
- A maiden lithium resource estimate is targeted for the first quarter of 2027.
- Civil works have started at the Lionheart Lithium Extraction Plant.
- First Lionheart production is targeted for the second half of 2028.
Vulcan Energy Resources (ASX:VUL) announced on 19 November 2026 that it had secured the Landau-Ost geothermal and lithium exploration licence in Rhineland-Palatinate, Germany. The licence has a five-year term and sits in the Upper Rhine Valley Brine Field, directly adjacent to Lionheart, the company's project under construction.
A New Licence Beside the Build
Vulcan describes the licence as a strategic upgrade to its portfolio. The licence area was not stated in the announcement material reviewed. The Upper Rhine Valley is one of Europe's main geothermal regions, where hot, mineral-rich brines circulate at depth.
Vulcan's model is to pump that brine to surface, use its heat for power and district heating, remove lithium, and reinject the brine. Additional licence ground in the same brine field can therefore matter for both lithium Supply and the renewable energy side of the business.
What Vulcan Plans
Vulcan Energy (ASX:VUL) has begun analysing available subsurface data and is targeting a maiden lithium resource estimate in the first quarter of 2027. That is a target rather than a result: no resource currently exists for Landau-Ost, and no drilling plans were set out.
After the resource estimate, the company intends to study development options, which could include a tieback to Lionheart so that brine or heat is linked into infrastructure already being built. Vulcan says available subsurface information indicates the geology is consistent with Lionheart.
Construction at Lionheart
Around 17 November, Vulcan said civil construction had started at the Lionheart Lithium Extraction Plant. The scope covers foundations and concrete for buildings, process equipment, utilities and the tank farm, plus site roads and drainage, following completed bulk earthworks. Chief executive Cris Moreno said the start of civil works completed all major execution milestones set for 2026.
The extraction plant is the first processing step, using Vulcan's VULSORB technology to extract lithium chloride from geothermal brine. The intermediate would then be converted to battery-grade lithium hydroxide at a Downstream plant at Frankfurt-Höchst. Vulcan (ASX:VUL) says the next stage is erection of buildings and delivery of process equipment.
Targets and Open Points
Lionheart targets 24,000 tonnes per year of lithium hydroxide monohydrate, with 275GWh of renewable power and 560GWh of heat a year for local consumers, over a 30-year project life. The company reports take-or-pay offtake contracts with European-focused buyers and targets first production in the second half of 2028. These are targets rather than achieved output, and commercial-scale geothermal lithium extraction is not yet established in Europe.
Vulcan Energy Resources (ASX:VUL) did not detail the financing package, the civil works contractor or the Landau-Ost licence area in the material reviewed. Disclosed milestones are the maiden resource estimate, a development Options study, continued construction through 2027 and first production in 2028. Mr Moreno has said the 2027 focus is execution discipline and advancing construction.
Key Insights
Vulcan (ASX:VUL) has extended its licence position beside Lionheart. Its value depends on the resource work due in 2027, and Lionheart production remains a 2028 target.