Highlights

  • Kinetiko expects to submit a Bulk Sampling Permit application to PASA at the end of October 2026, with grant anticipated in Q1 2027.
  • A Production Right Application is being prepared over all of Exploration Right 271, with the supporting Environmental Impact Assessment underway.
  • Contract award and front-end engineering design for the modular CNG facility are scheduled for Q4 2026.
  • Three potential Cluster 2 well sites have been shortlisted, with drilling planned to start early in 2027.

Kinetiko Energy Ltd (ASX:KKO) announced on 13 October 2026 that it has advanced production permitting and Phase 1 development at its Brakfontein project in South Africa. The update covers progress on Phase 1 of the Brakfontein Rolling Cluster under the company's Field Development Plan, including permit applications, infrastructure procurement, the next well location and the appointment of a new Chief Executive Officer.

Kinetiko is commercialising its 100%-owned shallow conventional gas projects in South Africa.

Bulk Sampling Permit and Production Right Application

The company stated that its Bulk Sampling Permit (BSP) application has been prepared and is being finalised, with submission to the Petroleum Agency of South Africa (PASA) expected at the end of October 2026. Kinetiko expects the approval process to take three to four months, with grant anticipated in Q1 2027. The BSP would allow limited gas production and sales before a Production Right is granted.

In parallel, Kinetiko is preparing a Production Right Application (PRA) covering all of Exploration Right 271 (ER271). The PRA is designed to support multiple production clusters under the company's Rolling Cluster Development Strategy. The supporting Environmental Impact Assessment has commenced, and its first stage, the drilling of water monitoring wells, has been completed.

Executive Chairman Adam Sierakowski described the BSP application as a key step towards first gas and said the company is making steady progress across its workstreams to move Brakfontein from exploration to production.

Phase 1 CNG Infrastructure and Cluster 2 Well Planning

Concept design for the Brakfontein Phase 1 Cluster has been completed and detailed engineering is underway. Phase 1 will connect existing Brakfontein wells to a central manifold and a mobile, modular Compressed Natural Gas (CNG) facility. A preferred supplier has been shortlisted for the CNG facility, with contract award and front-end engineering design (FEED) scheduled for Q4 2026.

For the next well, detailed subsurface evaluation including geological and reservoir modelling has been completed to guide placement. The well will support the second production cluster, known as Cluster 2. Three potential sites have been shortlisted, with final selection planned to enable drilling early in 2027. Procurement of long-lead items is progressing, with delivery scheduled for February 2027.

Mr Sierakowski noted that engineering and procurement for the Phase 1 CNG cluster are advancing and that narrowing down the next well location will inform Cluster 2.

Leadership, Land Access and Project Background

The search phase for a new Chief Executive Officer has been completed, with three candidates shortlisted. Kinetiko expects to complete the selection process in October 2026, with the new CEO to lead the company's transition from explorer to producer.

Discussions on land access compensation are progressing with several renewable energy companies whose project footprints may overlap ER271 or ER272. These follow a Co-operation and Settlement Agreement with Mulilo relating to the Newcastle wind energy facility, under which wholly owned subsidiary Afro Energy (Pty) Ltd will receive non-dilutive cash consideration equivalent to A$1.26 million in Rand.

Brakfontein is Kinetiko's flagship project and holds independently certified 2P reserves and a 2C contingent resource base of approximately 6 trillion cubic feet. The company describes a staged development path from initial CNG production through to full-field LNG at scale, in what it identifies as South Africa's primary power-producing region. The company noted that its timelines depend on factors outside its control, including regulatory timeframes.

The company's stated next steps are to submit the BSP application to PASA at the end of October 2026, continue preparing the PRA over ER271 and the supporting EIA, award the modular CNG facility contract and begin FEED in Q4 2026, finalise the Cluster 2 well site in Q4 2026 with long-lead items due in February 2027, and complete the CEO appointment.

Key Takeaways

  • Kinetiko plans to lodge its Bulk Sampling Permit application with PASA at the end of October 2026, with grant anticipated in Q1 2027.
  • A Production Right Application over all of ER271 is in preparation, supported by an Environmental Impact Assessment now underway.
  • Contract award and FEED for the modular CNG facility are scheduled for Q4 2026, with long-lead items for the Cluster 2 well due in February 2027.
  • Three CEO candidates have been shortlisted, with selection expected to be completed in October 2026.