Key Highlights

  • Stimulation of Pitse Pilot well 3.2 started on 23 November to accelerate gas build-up at production well 3.5B
  • Production well 3.5B reached 42 Mscf/day (~45 GJ/day) on 10 November before a downhole sensor replacement
  • Well 3.3 stimulation planned for early December to test the Upper Morupule, a second coal seam
  • BFS targeted for completion by end of 2026 for Board review in the new year

Botala Energy Ltd (ASX:BTE) has begun stimulation of Pitse Pilot well 3.2 at its Serowe Coal Bed Methane Project in Botswana. The stimulation is intended to accelerate gas build-up at the central production well 3.5B by drawing down reservoir pressure faster while adding a second producing well in the same Serowe coal seam.

Production Well 3.5B Performance

Well 3.5B has flowed gas continuously since 20 September 2026. Its measured average gas flow rate rose from about 1.5 Mscf/day to about 28 Mscf/day in October as the water level was drawn down from about 60m above the Serowe coal seam to about 10m. The well reached 42 Mscf/day (~45 GJ/day) on 10 November before being shut down to replace a downhole fluid level sensor.

Since restarting on 14 November, the well's gas flow rate has been rebuilding, reaching 29 Mscf/day on 23 November. The rate of gas flow has increased quickly due to the dewatering completed to date.

Well 3.2 Stimulation and Second Seam Testing

Well 3.2 sits in the same geological block as well 3.5B and targets the same Serowe seam. Stimulation started on 23 November following a recent perforation, with activities expected to take a week. Gas production from well 3.2 is targeted for early December.

Well 3.3, which is open to the Upper Morupule seam only, is planned for stimulation in early December. This well recorded the most notable pressure and water flow response at the Pitse Pilot following initial stimulation in February. If the Upper Morupule seam produces commercially useful gas, an additional well will be considered in 2027 to produce from both seams, potentially increasing gas production per well and reducing the number of wells needed for the planned 108-well first phase.

Path to BFS and Funding

The A$1.35 million Placement announced in October is funding the current field program, including the stimulation of wells 3.2 and 3.3, well work, and metering upgrades. A Share Purchase Plan for eligible shareholders closes on 27 November 2026. Production data from the Pitse Pilot wells is the key input to the Bankable Feasibility Study, which is due for completion by end of 2026 for Board review in the new year. An exploration well, BTE-1, is targeted to spud in January 2027.