Highlights

  • Conrad Asia Energy Ltd (ASX:CRD) traded at AUD 0.725 on October 7, 2026, up 9.85% during today's session.
  • Mako reached final Investment decision in March 2026, with first gas still targeted for Q4 2027.
  • More than US$290 million of project Capital contracts had been awarded by the end of July 2026.
  • Conrad reported first-half 2026 profit after tax of US$8.59 million and cash of US$3.26 million.

Trading at AUD 0.725 on October 7, 2026, Conrad Asia Energy Ltd (ASX:CRD) was up 9.85% during today's trading session. Conrad is a Singapore-headquartered Natural Gas exploration and development company with operated interests in offshore Indonesia. Its current focus is the Mako Gas Project in the Duyung Production Sharing Contract, alongside the Offshore North West Aceh and Offshore South West Aceh assets. Recent company reporting provides an update on Mako execution, funding arrangements and the financial position ahead of the targeted start of production.

Company Business

Conrad operates Indonesian natural gas Assets at different stages of development. Mako, located in the West Natuna Sea, is its principal development project. Following completion of the 2026 farm-down structure, Conrad is expected to hold a 22.875% operated effective participating interest in the Duyung PSC through West Natuna Exploration Ltd. The initial development plan comprises six subsea wells tied to a leased mobile offshore production unit, with gas transported through regional pipeline infrastructure to the Indonesian domestic market.

Conrad also holds 100% operated interests in the Offshore North West Aceh and Offshore South West Aceh PSCs. Together, these blocks cover about 20,000 square kilometres and contain existing shallow-water gas discoveries as well as additional exploration prospects.

Recent Development

In September 2026, Conrad released its interim report for the six months ended June 30. The report confirmed that Mako had moved into the execution phase following final investment decision in March. By the end of July, letters of award covering more than US$290 million of project capital contracts had been issued, representing over 90% of the estimated US$320 million development capex. First gas remained targeted for Q4 2027.

The company also completed a key step in the Nations Natuna Barat farm-down in late August 2026. Indonesian regulatory approval was received and completion triggered a US$4 million payment to Conrad. Together with the earlier US$5 million Tranche received in 2026, this left a further US$7 million payable upon commencement of commercial production. Under the agreed structure, Nations funds development capex, including the carried share associated with the retained project interest.

Financial Performance and Sector Context

For the six months ended June 30, 2026, Conrad reported no Revenue because its assets remain pre-production. Other income was US$13.17 million and profit after tax was US$8.59 million. Cash and cash equivalents stood at US$3.26 million at period end.

Net cash used in Operating Activities was US$11.04 million, while investing cash outflow was US$17.80 million, mainly reflecting expenditure connected with Mako. Financing activities generated US$30.75 million, including borrowing proceeds. The company remains exposed to the execution and financing characteristics of offshore gas development, including construction schedules, infrastructure readiness, gas pricing arrangements and regulatory requirements.

Risks to Consider

Mako remains in the development stage, creating execution exposure across engineering, fabrication, drilling, installation and commissioning. Delays or cost changes could affect the project timetable. Conrad also operates within Indonesia's regulatory framework, while the pre-production Business remains dependent on partner performance, financing arrangements and delivery of contracted infrastructure. The Aceh assets require further technical and commercial work before any development decisions.

What to Watch Next

Investors may monitor Mako construction and drilling milestones, any change to the US$320 million development cost estimate, and progress toward first gas in Q4 2027. Other points include the remaining US$7 million farm-down payment linked to commercial production, further updates on Conrad's effective Duyung interest and commercialisation activity across the Aceh PSCs. Future quarterly and full-year reports should provide additional detail on cash movements, borrowings and project execution.

Key Insights

Conrad has moved Mako from investment decision into project execution, with most of the planned capital contract value awarded by late July 2026. The company recorded a first-half profit but remains pre-revenue and continues to deploy cash into development activity. Separately, CRD shares were up 9.85% on October 7, 2026. The main factors to monitor are delivery against Mako's current cost and schedule framework, the Q4 2027 first-gas target and progress across the wider Indonesian portfolio.