Key highlights

  • Botala Energy (ASX:BTE) commenced stimulation of Pitse Pilot well 3.2 on 23 November 2026.
  • Production well 3.5B reached 42 thousand standard cubic feet of gas per day before a sensor replacement.
  • Stimulation of well 3.3 is planned for early December to test the separate Upper Morupule coal seam.

Botala Energy (ASX:BTE) traded at AUD 0.037 during the 24 November 2026 trading session, representing a decline of 15.91%. The S&P/ASX 200 was 1.62% higher at 8,709.20 points. Its Business centres on coal bed methane exploration and development at the Serowe project in Botswana. The company announced the start of stimulation at pilot well 3.2 on 24 November 2026.

Second well targets the Serowe seam

Botala announced on 24 November that stimulation had begun at well 3.2, following its recent perforation. The work is expected to take approximately one week, with gas production targeted for early December. Well 3.2 is located in the same geological block as central production well 3.5B and targets the same coal seam. The company intends to remove water from both wells to lower reservoir pressure across their shared area.

In coal bed methane production, gas is released from the coal as pressure falls. The pilot programme is designed to assess how the wells respond to dewatering and stimulation. Botala expects the additional well to assist the build-up of gas production at 3.5B, although the resulting rate has yet to be established through field measurements. The new well is also intended to provide a second source of gas from the Serowe seam.

Well 3.5B resumes gas flow after sensor replacement

Well 3.5B began flowing gas on 20 September 2026. During October, its measured average gas flow rose from approximately 1.5 thousand standard cubic feet per day to around 28 thousand. Over the same period, the water level was reduced from approximately 60 metres above the coal seam to around 10 metres above it.

The well reached 42 thousand standard cubic feet per day, equivalent to approximately 45 gigajoules per day, on 10 November before being shut down to replace a downhole fluid-level sensor. Operations restarted on 14 November. By 23 November, the gas flow rate had recovered to 29 thousand standard cubic feet per day. The pilot remains in a dewatering and gas build-up phase rather than at an established long-term production rate.

Upper Morupule testing and sector context

Well 3.3 targets the Upper Morupule, a coal seam below the Serowe seam. Water production at the well has declined from approximately 80 to 12 barrels per day, and the water level has fallen below the top of the coal. Gas has been observed in produced water, while samples have been collected for independent analysis.

Coal bed methane projects rely on reservoir pressure management, permeability and the ability to maintain gas flow over time. Testing multiple seams is part of Botala's approach to evaluating potential well configurations. If commercial gas flow can be established from Upper Morupule, the company may consider a well targeting both seams during 2027. This remains contingent on the stimulation and flow testing outcomes.

Risks investors are watching

Pilot gas rates may vary as reservoir pressure, water levels and equipment conditions change. The recent sensor replacement illustrates the potential for interruptions during field testing. Gas flow from Upper Morupule has not yet been established, and the ability to produce commercially useful volumes from both seams remains uncertain. Longer-duration data will be required before the company can determine whether the pilot performance supports its planned development configuration.

What to watch ahead

The immediate milestones are completion of well 3.2 stimulation and the start of its targeted gas production in early December. Botala also plans to stimulate well 3.3 during that period. The response of well 3.5B to joint dewatering, together with the gas and water flow data from the other wells, will form part of the continuing reservoir assessment. A potential dual-seam well remains a later consideration rather than a committed development outcome.

Pilot testing remains the operational focus

Botala is progressing the Serowe pilot through a sequence of well interventions and reservoir monitoring. The November work adds another well to the dewatering programme, with subsequent testing required to assess sustained gas production and the contribution of the second coal seam.