Highlights

  • It reached its 250 TJ/day nameplate capacity in April 2026 as the final two compressors came online, after earlier commissioning.
  • In the September quarter gross rates exceeded 240 TJ/day for 20 days in August.
  • A statutory shutdown starting 4 September ran longer than planned because air-cooler leak tests failed, so the plant returned on 8 October and has averaged about 235 TJ/day since.
  • In the June 2026 quarter the plant averaged 121 TJ/day because of compressor problems, despite touching its peak rate.
  • Waitsia production reliability and maintenance remain relevant to FY27 operating performance.

Beach Energy Limited (ASX:BPT) produces oil and gas through Assets in Australia and New Zealand, including the Perth, Cooper and Otway basins. During 2026, its Waitsia gas operations and wider development programme remained central to production planning. The company’s results and quarterly updates distinguish installed gas-processing capacity from actual output, which depends on equipment availability, maintenance and field operations.

Waitsia Production and Plant Availability

Waitsia is a gas plant operated with Mitsui in the onshore Perth Basin. It reached its 250 TJ/day nameplate capacity in April 2026 as the final two compressors came online, after earlier commissioning. In the September quarter gross rates exceeded 240 TJ/day for 20 days in August. A statutory shutdown starting 4 September ran longer than planned because air-cooler leak tests failed, so the plant returned on 8 October and has averaged about 235 TJ/day since.

The ramp-up has not been smooth. In the June 2026 quarter the plant averaged 121 TJ/day because of compressor problems, despite touching its peak rate.

For the year to 30 June 2026, Beach reported sales Revenue of about $1.8 billion and underlying EBITDA of about $1.0 billion. Underlying net profit after tax was $355 million, down 21 per cent. Production was 19.4 MMboe, and the average realised gas price was $11.5 per gigajoule, up 7 per cent. Free Cash Flow after all spending was positive $146 million.

Financial Performance and Capital Commitments

The final Dividend was 2.0 cents per share fully franked, taking FY26 dividends to 3.0 cents. Beach also dropped its fixed payout guidance, saying dividends will be considered on an all-in free cash flow basis after growth capital spending. That is a significant change for income-focused holders.

FY27 guidance, unchanged at the October update, is production of 19.5 to 23.0 MMboe and Capital Expenditure of $600 million to $700 million. FY26 capex was $699 million. The wide production range reflects dependence on Waitsia reliability, drilling outcomes and weather: FY26 guidance was cut to 19.4 to 20.3 MMboe after severe rain in the Cooper Basin and Western Flank.

Funding, Risks and Next Steps

At 30 September 2026, net Debt was $425 million, up from $387 million at 30 June, mainly because of abandonment spending and the FY26 final dividend. Drawn debt was $630 million. Liquidity was $945 million, made up of $205 million cash, including $43.5 million of restricted insurance proceeds, and $740 million of undrawn facilities. Beach reported no hedging.

Principal risks include Waitsia uptime, since another outage would cut production and cash flow; Commodity prices and exchange rates; exploration failure; cost inflation; and weather in the Cooper Basin, where about 300 barrels of oil a day of Western Flank production remained offline because of flooding. There were also operational disruptions at the Otway Gas Plant in July and a scheduled outage at Moomba carbon capture.

Next signposts are the Otway Investment decision, Taroom Trough drilling results expected in the December quarter, the Cooper Basin exploration campaign, Waitsia rates over the coming months, and the half-year result in February 2027.

Key Insights

The Waitsia plant’s stated capacity does not by itself establish sustained production. Actual operating rates, maintenance outcomes and the allocation of capital across Beach’s assets remain important distinctions in assessing its 2026 disclosures.