Highlights
- Fenix Resources paid a one-cent Dividend during the September quarter while investing in Beebyn Mining and long-term operating infrastructure.
- Quarterly shipments reached approximately 1.097 million wet tonnes, below June as port disruptions and the Beebyn transition affected volumes.
- FY27 sales guidance remains 4.7 million to 5.3 million tonnes, with unit cash costs expected to improve during the second half.
- An October hedge-book settlement crystallised more than AUD 10 million across immediate proceeds and scheduled November settlement of contracts.
Fenix Resources Limited (ASX:FEX) mines iron ore and operates associated haulage and export logistics in Western Australia. Its shares traded at AUD 0.198, up 1.28%, on 17 November 2026. The company is balancing Shareholder distributions with Investment at Beebyn, while maintaining FY27 guidance despite higher September-quarter unit costs.
Beebyn Changes The Production Platform
Mining at Beebyn W10 commenced during the September quarter, adding to operations at W11. The new five-million-tonne annual capacity crushing and screening plant was commissioned after quarter-end, with ramp-up expected during the December quarter.
The Beebyn Hub ore reserve totals approximately 26.9 million tonnes at 60% iron. That reserve underpins more than five years of mine life at current production rates, according to the quarterly report.
Fenix is also studying the broader Weld Range project. A definitive feasibility study is targeted for the first half of calendar 2027. The study and longer-term expansion plans remain distinct from current operating capacity and approved annual guidance.
Quarterly Costs Reflect Transition And Shipping
The company shipped approximately 1.097 million wet tonnes across eighteen vessels, compared with approximately 1.299 million tonnes in June. Seasonal port disruptions and the operational transition reduced shipment volumes.
Group C1 cash costs increased to AUD 81.80 per wet tonne from AUD 79.90. That quarterly figure sits above the annual guidance range, reflecting fewer shipments and higher diesel costs during the investment phase.
FY27 guidance remains sales of 4.7 million to 5.3 million tonnes at C1 costs of AUD 70 to AUD 80 per wet tonne, free on board Geraldton. Management expects costs to improve in the second half as volumes normalise and the new plant reaches full capacity.
Hedge Settlement Adds Cash After Quarter-End
On 23 October, Fenix announced early settlement of its Australian-dollar iron ore swap book, which covered 480,000 tonnes between October 2026 and June 2027.
Contracts for November through June were monetised for approximately AUD 8.5 million, expected during October. October contracts were due to settle in November at an indicated value of approximately AUD 1.7 million.
Remaining hedges include diesel swaps and Australian-dollar call options. Their quoted mark-to-market values are different from cash already collected. The diesel book covers 13.5 million litres, or approximately 30% of expected FY27 use, while currency Options provide protection against a stronger Australian dollar.
Distributions Sit Alongside Capital Requirements
Fenix paid a one-cent-per-share dividend during the September quarter. Cash at 30 September was AUD 43.2 million, down from AUD 81 million at June-end following major investment, with a further AUD 17 million of shipment proceeds received in early October.
Capital commitments included a second AUD 20 million right-to-mine payment. The Quarterly Report describes this period as the peak FY27 investment phase, while the new infrastructure supports future production and cost objectives.
The near-term priorities are plant ramp-up, shipment delivery and execution within annual guidance. Iron ore prices, fuel costs, weather-related port availability and commissioning performance remain relevant to cash generation. Market Capitalisation was AUD 152.21 million on 17 November; the shares were down 54.07% over one year.