West Wits Mining Limited (ASX: WWI) has announced a major operational milestone with the breakthrough of its 1 West Decline into the 2 Level mining horizon at Qala Shallows in the Witwatersrand Basin, South Africa. The achievement transitions the gold development project from initial diluted development ore into historically pre-developed underground workings containing established, unmined stoping areas. With a fully funded project finance package now executed and first drawdown completed, the company is advancing toward its steady-state production target while simultaneously progressing exploration at its Bird Reef Central uranium and gold project.
Key Points
- West Wits Mining Limited (ASX: WWI) achieved the breakthrough of its 1 West Decline into the 2 Level mining horizon at Qala Shallows in May 2026, unlocking access to historically pre-developed stoping areas
- Underground development reached 544 metres to 30 June 2026, with on-reef development ore deliveries yielding 4.6kg (148oz) of gold during the quarter and 7.05kg (227oz) year-to-date production
- Surface infrastructure is 45% complete with a new tarred access road completed and operational, permanent warehouse finished, and storm water management system implemented
- The company secured a full project finance package comprising ZAR 875 million Senior Loan Facility, ZAR 150 million Working Capital Facility, and ZAR 90 million Cost Overrun Debt Facility from Absa Bank and Nedbank CIB
- Cash position of approximately A$32 million as at 30 June 2026 provides funding for operations and growth projects including Bird Reef Central uranium and gold exploration programme
- Portfolio rationalisation through divestment of Mt Cecelia Project to Aventine Resources Limited under a value-accretive structure comprising equity, royalty, and milestone payments
- Expanded Scoping Study assessing multiple development and processing pathways including standalone processing plant, third-party processing partnerships, and additional ore source integration
West Wits Mining's Transition to Sustainable Gold Production in South Africa
West Wits Mining Limited is an ASX-listed gold development company advancing operations in the Witwatersrand Basin, Gauteng, South Africa. The company operates the Qala Shallows Project, a gold mining operation located in one of the world's most prolific gold-bearing regions. West Wits is progressing its transition to become a sustainable gold producer, with the Qala Shallows Project representing the company's primary asset and strategic focus. The company also holds the Bird Reef Central uranium and gold project, which it is developing as an organic strategic growth initiative.
The Witwatersrand Basin has been a significant gold-producing region for over a century, and West Wits is leveraging historical mining infrastructure and geological knowledge to accelerate its development timeline. The company's approach includes utilising pre-existing underground workings from historical mining operations, which reduces the capital and time required to establish mining access compared to developing new areas from greenfield status. This strategy is central to the company's project optimisation and business case, as demonstrated through the detailed feasibility study that underpins current operations.
1 West Decline Breakthrough and Access to Higher-Grade Stoping Areas
The breakthrough of the 1 West Decline into the 2 Level mining horizon represents a decisive operational milestone for West Wits Mining, achieved at the end of May 2026. This development transitions the Qala Shallows operation from initial diluted development ore extraction into historically pre-developed underground workings that contain established, unmined stoping areas requiring only minor modifications to accommodate modern trackless mining vehicles. The breakthrough was delivered through the Definitive Feasibility Study's mine plan optimisation, which was specifically designed to accelerate payback, improve capital efficiency, and strengthen the overall project business case.
Access to these historical working areas is estimated to save approximately one year of additional development work that would otherwise have been required to establish equivalent access to new stopes. Rather than continuing to mine lower-grade on-reef development ore, the operation can now begin accessing higher-grade production areas to improve mine grades and cash generation during the ramp-up phase. This transition accelerates progress toward the Definitive Feasibility Study-modelled steady-state production profile of approximately 70,000 ounces per annum, positioning the company to achieve improved financial returns and faster pathway to positive cash flow.
Underground Development Progress and Early Production Delivery
West Wits Mining has made substantial progress on underground development at Qala Shallows, with 544 metres of underground development completed to 30 June 2026. This development comprises 375 metres of on-reef development and 168 metres of waste development, demonstrating consistent advancement of the mine plan. The company's underground operations have begun producing ore that is being delivered to Sibanye Stillwater Ltd's Ezulwini Plant for processing, establishing the production pipeline ahead of the planned ramp-up to steady-state operations.
During the quarter, the early development ore deliveries to the Ezulwini Plant yielded 4.6 kilograms (148 ounces) of gold, with year-to-date production reaching 7.05 kilograms (227 ounces). These early production results validate the operational capability and ore quality assumptions underpinning the project development plan. The company's expansion of underground fleet capacity through delivery of two 10-tonne Load-Haul-Dump (LHD) vehicles and a third Jumbo drill rig during the quarter reflects the company's investment in mining flexibility and capacity to support accelerated development rates as the operation progresses.
Surface Infrastructure Development Advancing Toward Operational Readiness
Surface infrastructure development at Qala Shallows has progressed substantially, with 45% of all works now complete as at 30 June 2026. The completion of the new tarred access road provides direct access from the main public road into the mine and has significantly improved logistics, traffic flow, and site accessibility. This infrastructure improvement strengthens operational capability and supports continued ramp-up of mining activities as the project advances toward steady-state production. The permanent warehouse has been completed and is now operational, providing essential storage and logistics support for mining operations.
The company has also completed excavation of the pollution control dam and advanced storm water management systems, reflecting the integrated approach to environmental and operational infrastructure. The operations precinct is now well established with offices, workshops, stores, security and access control facilities, and other key operational buildings. These milestones represent the achievement of critical infrastructure requirements necessary to support sustainable mining operations and demonstrate the company's progress in establishing a modern mining operation within the Witwatersrand Basin.
Comprehensive Project Finance Package Executed with First Drawdown Completed
West Wits Mining has completed execution of a comprehensive project finance package comprising three distinct facility components totalling ZAR 1.115 billion. The finance structure includes a ZAR 875 million Senior Loan Facility, a ZAR 150 million Working Capital Facility, and a ZAR 90 million Cost Overrun Debt Facility, all arranged with Absa Bank and Nedbank CIB, two of South Africa's leading corporate and investment banks. The completion of this finance package represents a significant milestone in the company's development, providing the capital foundation for full project implementation and growth initiatives.
The company achieved first drawdown of the Senior Loan Facility during the quarter, enabling commencement of full-scale project funding. This funding achievement follows the company's repayment of the Nebari Loan Facility (USD 12.5 million) in full, which had been drawn as bridge funding in September 2025 to advance Qala Shallows development until the institutional finance close. The cash position of approximately A$32 million as at 30 June 2026 demonstrates the company's funding security and capacity to execute operational priorities including accelerated development rates, production ramp-up, and execution of expanded scoping studies.
Expanded Scoping Study Defining Multiple Pathways to 200,000 Ounces per Annum Production
West Wits Mining has expanded the scope of its Scoping Study to assess multiple development and processing pathways across the Witwatersrand Basin Project. The expanded assessment includes evaluation of construction of a standalone processing plant, third-party processing partnerships, and integration of additional ore sources beyond the Qala Shallows operation. This comprehensive evaluation is designed to identify the optimal pathway to achieve the company's ambitious production target of 200,000 ounces per annum, representing a significant increase from the Definitive Feasibility Study-modelled steady-state production of approximately 70,000 ounces per annum.
Results from the consultant are expected to be received by end of July 2026, with public release anticipated in early August 2026. The expanded Scoping Study represents the company's strategic approach to evaluating growth opportunities within its asset portfolio and the broader Witwatersrand Basin, leveraging the company's access to infrastructure, historical workings, and geological expertise. The outcomes of this study will be critical in defining the company's medium-term growth strategy and capital allocation priorities beyond the current Qala Shallows development phase.
Bird Reef Central Uranium and Gold Project Advancing With Exploration Programme Planning
West Wits Mining is finalising plans for implementing an exploration programme at the Bird Reef Central (BRC) Uranium and Gold Project, targeting a declared Uranium JORC Mineral Resource Estimate. The drawdown of the Senior Loan Facility has enabled allocation of surplus capital toward this growth project, reflecting the company's strategic intent to develop BRC as an organic strategic growth initiative alongside the core Qala Shallows operation. The project represents an opportunity for the company to build exposure to uranium and gold within the Witwatersrand Basin, a region with significant mineral endowment and historical production.
The allocation of capital toward BRC exploration demonstrates management confidence in the project's potential and the company's financial capacity to pursue multiple strategic initiatives. The exploration programme planning stage indicates that formal drilling and resource definition work is advancing toward commencement, with the declared JORC Mineral Resource Estimate representing a key milestone in the project's development pathway. This approach allows West Wits to build value from its exploration assets while maintaining operational focus on the core Qala Shallows development.
Portfolio Rationalisation Through Mt Cecelia Project Divestment
West Wits Mining has executed a sale agreement to divest the Mt Cecelia Project to Aventine Resources Limited under a value-accretive structure. The divestment comprises A$2.0 million in Aventine equity, a 1% net smelter royalty (NSR), and A$1.0 million in milestone consideration upon definition of a 500,000-ounce gold JORC Resource. This portfolio rationalisation transaction is designed to unlock value from the Mt Cecelia asset whilst maintaining exposure to potential upside at zero ongoing cost through the royalty and milestone components.
The transaction reflects the company's strategic focus on the Witwatersrand Basin assets and represents a capital-efficient approach to divesting non-core exploration assets. By transferring Mt Cecelia to Aventine, a West Australian-focused explorer, the company enables focused development by a specialist operator whilst retaining participation in future value creation. This approach optimises capital allocation by redirecting resources toward the company's core Qala Shallows production operation and strategic BRC growth project.
Capital Structure Consolidation Improving Institutional Readiness
West Wits Mining completed a capital consolidation on a 10-for-1 basis, reducing shares on issue to 434,647,512 ordinary shares. This capital structure adjustment improves the company's institutional readiness ahead of the completed project finance close and positions the company with a more efficient capital structure. Capital consolidations of this nature are typically undertaken to improve share register metrics and enhance the acceptability of the security to institutional investors and financial institutions.
The consolidation reflects the company's maturing status as a development-stage project advancing toward production operations. A more efficient share structure typically improves trading characteristics and facilitates institutional participation in future equity raises or strategic transactions. The timing of the consolidation coinciding with the completion of major project finance and operational milestones demonstrates the company's integrated approach to corporate governance and capital management as it transitions from development to operational phases.
Investor Considerations and Operational Outlook
West Wits Mining has announced clear operational priorities for the next quarter, including advancement of development rates, ramp-up of production, and execution of the expanded Scoping Study to define the pathway to 200,000 ounces per annum production. The company's achievement of the 1 West Decline breakthrough, completion of comprehensive project finance, and advancement of surface infrastructure represent significant progress against the development timeline. The secured funding structure and positive early production results provide a foundation for accelerated operational advancement.
Investors may be watching the company's progress on several key metrics including quarterly development metres, ore grade delivered to the processing plant, production ounces per quarter, and advancement of the surface infrastructure completion timeline. The outcomes of the expanded Scoping Study and the company's definition of the pathway to 200,000 ounces per annum will likely influence investor perceptions of the company's growth strategy and long-term value potential. The company's management has indicated that finalising project finance enables pursuit of the standalone BRC Uranium and Gold Project exploration programme, suggesting a multi-asset development strategy under active evaluation.