VBX Limited (ASX:VBX) delivered its Chairman's address at the company's Annual General Meeting on 20 November 2026, disclosing an updated Mineral Resource Estimate of 143.2 Mt for the Wuudagu Bauxite Project, an expanded Definitive Feasibility Study scope, and the completion of a $4.5 million placement.

Key Points

  • Updated Wuudagu Mineral Resource Estimate of 143.2 Mt, including 131.9 Mt in the Measured and Indicated categories, representing a 108% increase over the resource on which the 2025 Preliminary Feasibility Study was based
  • DFS mining and beneficiation rate scope increased from 6 million tpa to between 8 and 9 million tpa
  • Metallurgical optimisation test work returned a 23% increase in recovery of bauxite product with 45.4% alumina content and 3.6% silica content
  • $4.5 million placement completed in October, with proposed conversion of $2.5 million shareholder loans to equity at the same placement price, subject to shareholder approval
  • DFS completion extended to the first quarter of the 2027 calendar year

Wuudagu Mineral Resource Estimate and Metallurgical Test Work

According to the filing, VBX's 2025 infill and exploration drilling program resulted in an updated Mineral Resource Estimate of 143.2 Mt for the Wuudagu Bauxite Project, with 131.9 Mt in the Measured and Indicated categories. The company disclosed this represents a 108% increase in resource size compared to that underpinning the 2025 Preliminary Feasibility Study. Metallurgical optimisation test work also demonstrated, using the same criteria as the PFS, a 23% increase in recovery of a bauxite product with 45.4% alumina content and 3.6% silica content, while maintaining low-silica characteristics. The filing noted that recovery varies according to scrubber screen size and residence time of ore in the beneficiation plant.

Definitive Feasibility Study Scope and Timeline

The filing states that the expanded resource and improved metallurgical recoveries have allowed the company to increase the DFS mining and beneficiation rate from 6 million tpa to between 8 and 9 million tpa, incorporating higher mass recovery of the Wuudagu high alumina, low silica bauxite product. As a result of incorporating these and other improvements into the DFS scope, the company has extended the time to completion of the DFS to the first quarter of the 2027 calendar year. The filing also states the company does not see this extension as having a material effect on its ability to secure necessary approvals through the 2027 calendar year and achieve first production in 2028.

Placement, Shareholder Loans and Team Appointment

The company disclosed that a $4.5 million placement was completed in October to maintain the Wuudagu project's momentum. Subject to shareholder approval at the AGM, the company also proposed the conversion of $2.5 million in shareholder loans to equity at the same price as the placement. The filing noted that a formal process has been initiated to assess preliminary operating, infrastructure and offtake-linked funding proposals, with the intention of finalising a development funding solution following DFS completion. The company also disclosed that Vivienne Powe, a metallurgical engineer with senior mining industry executive experience including project development, operations and corporate finance, has transitioned to a technical executive director role.