Unico Silver Limited (ASX:USL) has rescheduled its maiden integrated Pre-Feasibility Study (PFS) for the 100%-owned Joaquin and Cerro Leon silver-gold projects in Santa Cruz Province, Argentina, from September 2026 to January 2027, according to a company filing dated 18 August 2026.

Key Points

  • PFS rescheduled from September 2026 to January 2027 to incorporate an updated Mineral Resource Estimate and additional metallurgical process work.
  • Infill and extensional drilling completed since March 2026 at La Negra SE, La Morocha SE and Breccia Puntudo will be incorporated into the updated Mineral Resource Estimate.
  • All process trade-off studies are now complete, with additional metallurgical and process design testwork nearing completion.
  • Heap-leach column testwork to assess a secondary processing route for low-grade material is underway, with preliminary results pointing to improved recoveries.
  • The company continues to target RIGI inclusion by the second half of 2027.

PFS Rescheduling and Revised Scope

The revised PFS timeline will allow Unico Silver to incorporate an updated Mineral Resource Estimate that reflects infill and extensional drilling completed since March 2026 at La Negra SE, La Morocha SE and Breccia Puntudo. The company also disclosed that further infill drilling is currently underway in select areas with the aim of maximising resource-to-reserve conversion. According to the filing, all process trade-off studies have now been completed, and these have identified a series of alternative process options relating to project scale and capital intensity.

Heap-Leach Testwork and Metallurgical Progress

Additional metallurgical and process design testwork is described as nearing completion, including heap-leach column testwork assessing a secondary processing route for low-grade material. The filing states that preliminary results from this testwork point to improved recoveries that could affect resource scale, process design and the production profile. The company said the additional testwork is intended to underpin a higher-confidence study that feeds directly into its RIGI application and environmental approvals, with reduced risk of later change to the study's findings.

RIGI Inclusion Target and Project Overview

Unico Silver stated it continues to target inclusion under the RIGI framework by the second half of 2027. The Joaquin and Cerro Leon projects are 100%-owned by the company and are located in Santa Cruz Province, Argentina. Managing Director Todd Williams said in the filing that rescheduling the PFS would allow additional infill drilling in key areas to convert Inferred pit-constrained ounces to the Indicated category, with the aim of maximising the maiden Ore Reserve. The filing was authorised for release by the Board of Directors of Unico Silver Limited.